SMARTZONE UPS INSTALLATION MANUAL
43
c. Insert the connectors back into the middle hole on the chassis.
d. Reinstall and secure the retained battery covers in reverse order of above
step.
e. Place the unit into its own tower kit to the right of the UPS. The EBP Battery
Pack signage does not rotate.
f. Reinstall the faceplate on the EBP, by aligning the front panel latches with the
holes in the front of the unit and snapping the faceplate onto the front of the
EBP unit. Should have a positive snap of the latches on the faceplate.
3U Units (U05N11V, U05S11V, U06N11V, U06S11V, U06N12V,
U06S12V, U10N11V, U10S11V, U10N12V, U10S12V, UVP240)
1. Assemble the tower kit with one extender for each set of tower feet:
a. Align to interlock a tower foot and one extender at a right angle and rotate to
snap together.
b. Then align to interlock the tower foot with the extender to the second tower
foot at a right angle and rotate to snap together (see figure below).
Figure 63: Tower Kit for 3U Units
c. Place the UPS in the tower kit, the UPS LCD does not physically rotate, it will
rotate electronically (see SmartZone 5-20kVA User Manual for details).
d. Install the faceplate on the UPS unit, by aligning the front panel latches with
the holes in the front of the unit and snapping the faceplate onto the front of
the unit. Should have a positive snap of the latches on the faceplate (see figure