SMARTZONE UPS INSTALLATION MANUAL
32
Figure 43: Secure the Mounting Brackets to the Rack
Install 4U EBP Unit (UVP480)
It is recommended to install the EBP unit directly under the UPS unit. It is recommended
to install all subsequent EBP units directly under the previous EBP.
1. Install the URM480 rail kit:
a. Install the 8x M5 cage nuts in the rack front equipment rail, with square holes.
One behind the holes in each rail kit rail. One behind the slot in the in each rail
kit rail. One behind the first equipment rail hole above each rail kit rail (see
figure below).
Figure 44: Install Cage Nuts in the Front Equipment Rail with Square
Holes
b. Install the 4x M5 cage nuts in the rack rear equipment rail, with square holes.
One behind the lowest slot in each rail kit rail and one behind the third slot
(one down from the top slot) in the in each rail kit rail (see figure below).