background image

INSTALLATION INSTRUCTIONS     PN79G

 © Panduit Corp. 2007

For Technical Support: www.panduit.com/resources/install_maintain.asp

Page 1 of 2

4. Install jumper troughs between bases with two #12 sheet metal 

screws (supplied).

P

AN

-P

UNCH

 

110 Tower System

NOTE:  300 PAIR TOWER SHOWN.  INSTRUCTIONS ALSO APPLY TO THE 900 PAIR TOWER.

CABLE REQUIREMENT: Terminates most 22-26 AWG solid or stranded

 IWC wire with a .050" (1.27mm) max. o.d., either PVC or Plenum rated.

1. Mount tower to wall using #12 wood screws (not  provided) or 

equivalent. Some applications will require different mounting 
hardware. Ensure that the bottom of the tower is at least 8" from 
the floor to provide space for horizontal cable manager trough.

2. Route cable bundle into tower and fan out individual cables into

their appropriate positions through the cutouts provided along the 
tower leaving 12" to 18" of slack. Each cutout  accommodates up 
to 25 pair. Use cable ties to secure bundle to raised tabs on back 
of tower.

3. Position base over slots in tower and secure with two #12   

sheet metal screws (supplied). Place conductors into index   
strip and install connecting blocks as per instruction sheet 
PN51* (provided).

SCREW HERE

SCREW HERE

* Denotes instruction sheet revision letter.

Отзывы: