9
•
Repeat steps
6
to
9
for "S3" through "S5".
Step 9 - Locating the IP-CSs
Locate the IP-CSs in the positions established in the site survey.
Step 10 - Confirming the Status of Air Synchronization
Follow the directions indicated on the PC Maintenance Console.
1
2
A
B
•
Monitored Level
: Between "7" and "11".
Notice
If the monitored level is not between "7" and "11", relocate the IP-CS.
Step 11 - Registering PSs
Refer to "10 Registering Portable Stations".
Step 12 - Testing PS Operation
Walk around the service area while having a conversation using a registered PS. If noise is frequent or the
conversation is disconnected, relocate the IP-CS or install an additional IP-CS.
Step 13 - Wall Mounting
Refer to "11 Wall Mounting".