IG-308-EN version 01; 03/06/2022
61
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
Recommended sequence of operations
5.6.5. Incoming earthing function
cgm
.3-huv-rbv
Opening operation from earthing position
Initial conditions: circuit-breaker open and earthing switch
S1 closed.
1.
Select using the lever or check the position of the
selector handle in position S1.
Figure 5.61.
Selector handle detail
2.
Move the earthing switch's actuating shaft access
handle to position S1.
Figure 5.62.
Detail of S1 earthing switch access handle