In order to achieve high levels of functionality and machining accuracy, as well as a long
service life of the machine, the set-up location should meet certain criteria.
The following points should be noted:
The device must only be installed and operated in a dry and well-ventilated place.
Avoid places close to machines which cause chips or dust.
The installation site must be vibration-free, i.e. located away from presses, planing
machines, etc.
The substructure must be suitable for milling machines. Pay attention also to the load-bear-
ing capacity and evenness of the floor.
The substructure must be prepared in such a way as to ensure that, if any lubricant is used,
it cannot penetrate the floor.
Protruding parts - such as the dog, handles, etc. - must be secured, where necessary, by
means of on-site measures so that persons are not endangered.
Provide enough space for set-up and operating personnel and material transport.
Also bear in mind accessibility for installation and maintenance works.
Ensure adequate lighting is available (minimum value: 500 Lux, measured at the tool tip). In
the event of a lower level of lighting, additional illumination must be provided, e.g. by means
of a separate workplace light.
INFORMATION
The main switch of the milling machine must be freely accessible.
3.5
Machine fixing
3.5.1 Anchor-free mounting
Provide a solid substructure at each support point of the levelling points between the foundation
and the machine foot or use adjustable feet (2) with adjusting screws (3) from the delivery.