5.1.1 SET FUNCTION TEST
Configuration screen for the automatic function test of the connected points. Frequency and time of the test
can be adjusted. There is the option to apply this setting to all panels of the
panel network
or to the current
panel only. The test is performed on the selected time for the selected days of the week. At least one day
must be selected.
Figure 31
5.1.2 SET DURATION TEST
Configuration screen for the two automatic duration tests of the connected points. Each test can ne
enabled/disabled and its date and time can be configured. There is the option to apply this setting to all panels
of the
panel network
or to the current panel only. It is recommended to perform the test twice a year, once
every 6 months and not at the same time with a function test.
Figure 32
5.1.3 START FUNCTION TEST
Menu to start a manual function test for all zones or a specific one. There is the option to send this command
to all panels of the
panel network
or to the current panel only.