Expert mode
»
Select “Operating program, screed drying program”.
»
Select “ON”.
27.7.2 Adjusting and starting the screed drying program
»
Go one step back to the heating circuit menu.
»
Select “Screed drying program”.
»
Select “Program selection”.
Note
The selection option is only available if the screed
drying program has been activated.
Note
Higher operating hours for the heat pump and the
electric auxiliary heater may lead to higher running
costs during the screed drying program.
»
Select the required program.
Program selection
Various selection options are available for the screed dry-
ing program:
Standard without test
The standard program consists of a heating phase, a holding phase
and a cooling phase.
The program is run for the period defined by your settings. No
checks are made as to whether the target temperatures are
reached.
X Days
Y Flow temperature
1 Target value
2 Heating phase 1
3 Holding phase
4 Cooling phase 1
Standard with test
The standard program consists of a heating phase, a holding phase
and a cooling phase.
The program is run. At the 23rd hour, the test is started. If the flow
temperature is within 2K of the target value for a total of 30 minutes,
the test is ended and the target temperature for the next day is set.
If the target value is not reached, the target temperature remains
unchanged until it is achieved. Only then will the program continue.
This can extend the screed drying program.
X Days
Y Flow temperature
1 Target value
2 Test phase
3 Heating phase 1
4 Holding phase
5 Cooling phase 1
6 End of test phase
Exclusive without test
The exclusive program consists of two heating phases, a holding
phase and two cooling phases.
In the second heating phase, the temperature rise per day is 10K.
This value cannot be adjusted.
The program is run for the period defined by your settings. No
checks are made as to whether the target temperatures are
reached.
X Days
Y Flow temperature
1 Target value
2 Heating phase 1
3 Holding phase
4 Cooling phase 1
5 Heating phase 2
6 Cooling phase 2
Exclusive with test
The exclusive program consists of two heating phases, a holding
phase and two cooling phases.
In the second heating phase, the temperature rise per day is 10K.
This value cannot be adjusted.
The program is run. At the 23rd hour, the test is started. If the flow
temperature is within 2K of the target value for a total of 30 minutes,
the test is ended and the target temperature for the next day is set.
If the target value is not reached, the target temperature remains
unchanged until it is achieved. Only then will the program continue.
This can extend the screed drying program.
Содержание AIR FALCON 212
Страница 7: ...BA 982018 AIR FALCON sh EN www ochsner com 7...
Страница 9: ...00_400_200_202_01_split_Funktionsweise EN www ochsner com 9 How split systems work...
Страница 65: ...OTS_EN www ochsner com 65 Expert mode...
Страница 77: ...OTS_ZSM_EN www ochsner com 77...
Страница 85: ...BA 982018 AIR FALCON EN07 www ochsner com 85...
Страница 86: ...Notes...
Страница 87: ...Notes...