background image

 

Document UT-MT-0708_EN 

Page 13 of 17 

 

Edition 11/03/2014 

Supersedes edition 11/14/2013 

LED ELEVATED HELIPORT LIGHT LHE 
INSTRUCTION MANUAL FOR USE, INSTALLATION AND MAINTENANCE 

 

 

4.1.1

 

Periodical Checks 

Daily 

Burnt-out luminous source 
Broken parts of lights 

Monthly 

Cleaning of the lenses 
Correct setting of the lights 

Semi-Annual 

Painting or replacement of rusted parts 

Annual 

Stability of the civil works 
Stability and assembly of lights 
Electrical connections and insulation degree 
Luminous efficiency of luminous sources 
Condition of all the gaskets 

Unscheduled 

After  unusual  atmospheric  precipitation,  check  the 
light  condition  and  remove  any  luminous  beam 
obstructions 

 

4.1.2

 

Snowplow Operations 

Snowplow  operators  should  exercise  extra  care  not  to  strike  the  light  fixtures  with 
snowplow blades. After snow removal operations, inspect all light fixtures to locate 
and replace, if necessary, any damaged light assemblies. 

 

4.2

 

 REMOVING AND OPENING THE LIGHT UNIT 

4.2.1

 

Removing the fixture 

Remove the fixture from base plate or pipe elbow following steps are suggested: 

 

unscrew the frangible coupling screw 

 

hold the fixture and unscrew the frangible coupling 

 

lay the fixture and disconnect plug to the secondary receptacle inside the pipe elbow 

 

disconnect the fixture grounding wire to the grounding wire coming from the pit (or from 
the base). 

4.3

 

LENS CLEANING 

4.3.1

 

Prism outside cleaning 

 

Removing  the  fixture  is  not  necessary  to  clean  the  outer  surface  of  the  prisms,  and  if 
already  removed  is  not  necessary  to  open  it.  Clean  the  lens  surface  with  non  abrasive 
glass product. 

Содержание LHE

Страница 1: ...IVERED BY MEANS OF THE AUTOMATIC KNOWLEDGE MANAGEMENT SYSTEM IT CAN BE SIGNED ON REQUEST THIS DOCUMENT AND THE DATA CONTAINED HERE IN IS PROPRIETARY PROPERTY AND SHALL NOT BE DUPLICATED USED OR DISCLO...

Страница 2: ...the applicable warranty period All costs of transportation of Products claimed not to be warranted and of those repaired or replaced to or from the facility of the Company shall be borne by Purchaser...

Страница 3: ...he unit opened the main circuit breaker and removed the supply to the unit by opening the circuit breaker switch on the distribution board at the beginning of the supply line Then wait discharge time...

Страница 4: ...AND MAINTENANCE EDITIONS Date 02 10 2013 11 14 2013 11 03 2014 First issue Updated chapter Cable lead with plug and List of the recommended spare parts New address of the Company Deleted List of the...

Страница 5: ...4 1 1 Periodical Checks 13 4 1 2 Snowplow Operations 13 4 2 REMOVING AND OPENING THE LIGHT UNIT 13 4 2 1 Removing the fixture 13 4 3 LENS CLEANING 13 4 3 1 Prism outside cleaning 13 4 4 LENS REPLACEME...

Страница 6: ...EN Page 6 of 17 Edition 11 03 2014 Supersedes edition 11 14 2013 LED ELEVATED HELIPORT LIGHT LHE INSTRUCTION MANUAL FOR USE INSTALLATION AND MAINTENANCE LIST OF ATTACHMENTS UC PU 0279 LIST OF THE RECO...

Страница 7: ...the pole using three screws These screws also allow the levelling of equipment the power supply control PCB and the LED circuit are mounted on the aluminium inner body steel 1 inch tube available in...

Страница 8: ...Document UT MT 0708_EN Page 8 of 17 Edition 11 03 2014 Supersedes edition 11 14 2013 LED ELEVATED HELIPORT LIGHT LHE INSTRUCTION MANUAL FOR USE INSTALLATION AND MAINTENANCE Figure 1 Exploded View...

Страница 9: ...ug 1 11 Fixture grounding wire 1 Figure 2 Part List LHE I G D 25 C P 0 Basic P N Compliance I ICAO IEC S STANAG Colour W White G Green Y Yellow Mode D Parallel Circuits 48 V Height 00 w o pole 25 250...

Страница 10: ...ting transformer is housed into a separate concrete pit which is normally placed close the above concrete block Figure 4 The pit can be placed far from the concrete block too but in this case a suitab...

Страница 11: ...inch tube over the fixture cable assembly cable leads with plug plus yellow green wire and into the fixture body until the body bottoms against the tube approach without tighten the set screws on the...

Страница 12: ...OFF DO NOT OPERATE ON LIVE PARTS LED lighting fixtures do not require frequent maintenance With well run installations and handling fixture carefully avoiding excessive falls or collisions the only ma...

Страница 13: ...Operations Snowplow operators should exercise extra care not to strike the light fixtures with snowplow blades After snow removal operations inspect all light fixtures to locate and replace if necess...

Страница 14: ...g ring Figure 6 Place a new gasket on the body Set the new lens on the body Hand tighten the locking ring Figure 6 Removing the Lens 4 5 LED MODULE REPLACEMENT Remove the lens with gasket as above des...

Страница 15: ...ew electronic and reassembly the unit with reverse procedure IMPORTANT IT IS SUGGESTED TO REPLACE THE LENS GASKET TO NOT AFFECT WATERTIGHTNESS 4 7 BREAKABLE COUPLING REPLACEMENT Unscrew the lower thre...

Страница 16: ...sert 4 8 2 Installing the new cable lead with plug Replace the cable gland if damaged Insert a new cable lead and a new grounding wire if necessary into the sealing insert at approx 8 cm from the free...

Страница 17: ...TIVE Replace the Power PCB Moisture inside the fixture Execute leakage test and replace damaged components Clean and dry the inside area of the fixture No connection of primary circuit Check transform...

Отзывы: