Chapter 3 — System and site requirements
553-3121-210
Standard 3.0
January 1999
Grounding requirements
Before installing the Option 11C Compact system and applying AC power,
measure the impedance of the building ground reference. (An ECOS 1023
POW-R-MATE or similar meter is suitable for this purpose.) If the ground
path connected to the Option 11C Compact has an impedance of 5 ¾ or more,
better grounding arrangements should be made. Any improvements to the
grounding system should be made before the system is installed.
Other grounding requirements are as follows:
•
The impedance of the link between the ground post of the system
cabinets and the Single Point Ground (SPG) to which it is connected
must be less than 0.25¾. Reliable system operation depends on
high-precision internal circuitry, which can be damaged by transients in
its supply conductors and ground system. Damage to sensitive devices
due to transients may not be immediately apparent: degradation may
occur over longer periods of time.
•
Do not connect the single point ground conductor from the Option 11C
Compact system to structural steel members or electrical conduit. In
particular, do not tie this conductor to a ground source or grounded
electrode that is not hard-wired to the building reference conductor.
•
Ground conductors for the Option 11C Compact system:
— must be a minimum of #6 AWG at any point
— must be routed through the same conduit as the phase conductors
serving the system
— must not be smaller than any phase conductor in the same conduit
— must not carry current under normal operating circumstances
•
All ground conductors in the building:
— must be isolated from the neutral bus except at the service entrance
to the building
— must be hardwired to the main ground reference
•
Avoid spliced conductors. Continuous conductors have lower impedance
and are more reliable than spliced ones.
Содержание Meridian Meridian 1
Страница 3: ...553 3121 210 Standard 3 0 January 1999 ...
Страница 17: ...xiv Contents 553 3121 210 Standard 3 0 January 1999 ...
Страница 89: ...Page 70 of 536 Chapter 6 Bracing cabinets against earthquakes 553 3121 210 Standard 3 0 January 1999 ...
Страница 97: ...Page 78 of 536 Chapter 8 Installing a new system 553 3121 210 Standard 3 0 January 1999 ...
Страница 107: ...Page 88 of 536 Chapter 10 Installing the system ground 553 3121 210 Standard 3 0 January 1999 ...
Страница 113: ...Page 94 of 536 Chapter 11 Installing the power supply 553 3121 210 Standard 3 0 January 1999 ...
Страница 125: ...Page 106 of 536 Chapter 12 Adding an expansion cabinet 553 3121 210 Standard 3 0 January 1999 ...
Страница 139: ...Page 120 of 536 Chapter 13 Installing the circuit cards 553 3121 210 Standard 3 0 January 1999 ...
Страница 157: ...Page 138 of 536 Chapter 15 Installing and connecting SDI and Ethernet ports 553 3121 210 Standard 3 0 January 1999 ...
Страница 175: ...Page 156 of 536 Chapter 16 Starting up and testing the system 553 3121 210 Standard 3 0 January 1999 ...
Страница 209: ...Page 190 of 536 Chapter 18 Connecting the trunks 553 3121 210 Standard 3 0 January 1999 ...
Страница 323: ...Page 304 of 536 Chapter 21 Installing Hospitality 553 3121 210 Standard 3 0 January 1999 ...
Страница 419: ...Page 400 of 536 Chapter 23 Pre programmed data 553 3121 210 Standard 3 0 January 1999 ...
Страница 455: ...Page 436 of 536 Chapter 24 Changing pre programmed data 553 3121 210 Standard 3 0 January 1999 ...
Страница 555: ...Page 536 of 536 Chapter 25 Fault locating and clearing 553 3121 210 Standard 3 0 January 1999 ...