Option 11C Compact
Planning, Installation, Fault Clearing and CCBR Guide
48
Chapter 3 — System and site
requirements
Before installing the Meridian 1 Option 11C Compact system, make sure that
the site meets all of the following environmental, grounding, power, and
cross-connect terminal requirements.
Environmental requirements
The Option 11C Compact system is designed to operate in an office
environment that meets the following general conditions:
•
The room is clean and well ventilated. Each cabinet dissipates up to 500
Watts of power in the form of heat (1700 BTU [1800 kJ] per hour).
Equipment room ventilation must be sufficient to maintain the
temperature at an acceptable level.
•
The temperature is maintained between 32° and 115°F (0°and 45° C)
when the cabinets are mounted side-by-side.
•
The humidity is maintained between 5% and 95% non-condensing.
•
The location selected to mount the equipment is not subject to constant
vibration.
•
The equipment is located at least 12 ft (4.5 m) from sources of
electrostatic, electromagnetic or radio frequency interference. These
sources include such things as:
— power tools
— appliances (such as vacuum cleaners)
— office business machines (such as copying machines)
Содержание Meridian Meridian 1
Страница 3: ...553 3121 210 Standard 3 0 January 1999 ...
Страница 17: ...xiv Contents 553 3121 210 Standard 3 0 January 1999 ...
Страница 89: ...Page 70 of 536 Chapter 6 Bracing cabinets against earthquakes 553 3121 210 Standard 3 0 January 1999 ...
Страница 97: ...Page 78 of 536 Chapter 8 Installing a new system 553 3121 210 Standard 3 0 January 1999 ...
Страница 107: ...Page 88 of 536 Chapter 10 Installing the system ground 553 3121 210 Standard 3 0 January 1999 ...
Страница 113: ...Page 94 of 536 Chapter 11 Installing the power supply 553 3121 210 Standard 3 0 January 1999 ...
Страница 125: ...Page 106 of 536 Chapter 12 Adding an expansion cabinet 553 3121 210 Standard 3 0 January 1999 ...
Страница 139: ...Page 120 of 536 Chapter 13 Installing the circuit cards 553 3121 210 Standard 3 0 January 1999 ...
Страница 157: ...Page 138 of 536 Chapter 15 Installing and connecting SDI and Ethernet ports 553 3121 210 Standard 3 0 January 1999 ...
Страница 175: ...Page 156 of 536 Chapter 16 Starting up and testing the system 553 3121 210 Standard 3 0 January 1999 ...
Страница 209: ...Page 190 of 536 Chapter 18 Connecting the trunks 553 3121 210 Standard 3 0 January 1999 ...
Страница 323: ...Page 304 of 536 Chapter 21 Installing Hospitality 553 3121 210 Standard 3 0 January 1999 ...
Страница 419: ...Page 400 of 536 Chapter 23 Pre programmed data 553 3121 210 Standard 3 0 January 1999 ...
Страница 455: ...Page 436 of 536 Chapter 24 Changing pre programmed data 553 3121 210 Standard 3 0 January 1999 ...
Страница 555: ...Page 536 of 536 Chapter 25 Fault locating and clearing 553 3121 210 Standard 3 0 January 1999 ...