INSTALLATION MANUAL 

ZHJS + ZHJ

C

INSTALLATION OF 

ZHJS + ZHJ

C

 FOOT ASSEMBLY

This guideline describes how to install the 

ZHJS + ZHJ

C

 foot 

assembly onto the machine or component for which it is intended 
to support.

0a.  Prior to installation of the foot ensure that the incline 

of the floor area intended to support the foot pad 

does not exceed 10 degrees relative to horisontal. 

0b.  Assure that the foot pad will not span over cracks, 

grout lines or other floor imperfections when 

mounted. If unavoidable the cavity between the 

load bearing foot and the floor must be sealed with 

injecting bonding material under and around the edge 
of the load bearing foot. 

1a.  Lift/Jack up the machine for free access to mount 

foot assembly.

1b.  Ensure that sealing is correctly mounted on top of 

the sleeve. Grease external thread with FoodLube 
Universal Grease. Make sure to remove any excess of 
grease from external surfaces after installation.

2.

Mount the machine foot on the machine and use a
wrench to adjust the vertical position. Make sure not
to exceed the max adjustable height and that the
length of engagement is correct.
Complete step 0-2 for all feet supporting the machine.

Lower the machine so that the feet rest on the floor.

 

Perform height adjustment if needed and ensure

 

that 

the 

machine is 

placed corretly and 

levelled 

horizontally

.

3.

Use a wrench to rotate and tighten the sleeve up
against the bottom of the machine or component for
which the foot is used. Make sure that the sleeve is
properly tightened to secure the foot assembly and to
prevent dirt from accessing the thread.

NB. If the sleeve does not cover the thread, the leg is not 

correctly installed and will neither meet hygienic 

guidelines nor load specifications.