background image

 

SKG Gas Fired Humidifier

 

 

SKG Start-up check list 180223 

www.neptronic.com

 

1/2 

Initial Verification 

 

Initial verification and start-up (commissioning) must be carried out by suitable 
qualified personnel. 

Clearance 

1.  Ensure that the humidifier cabinet is installed in a location where the humidifier 

can be serviced correctly. 

 

Electrical 

2.  Check  that  the  power  supply  (voltage)  conforms  to  the  appliance  name  plate 

on the humidifier side. 

 

3.  Confirm that 24Vac is present between tab 1&2 of the control terminal, located 

on the control connection PCB. Remove the front top cover to get to this PCB. 

 

Water 

4.  Ensure that water is supplied to the humidifier. A shut-off valve must be outside 

the humidifier.  
Once the water shut-off valve is turned ON, ensure that there are no apparent 
leaks.  

 

5.  Confirm  that  drain  piping  is  properly  connected  with  a  pitch  of  at 

least  ¼’’ 

(6.5mm) per foot (300mm) horizontal run. 

 

Steam 

6.  Check that steam distributors are properly installed into the ventilation duct. 

 

7.  Verify that the flexible steam hoses and rigid steam supply pipes are shorter in 

total  length  than  15ft  (5m),  properly  sloped  and  have  condensation  P  traps 
wherever required. 

 

Gas 

8.  Verify that a proper regulator and gas test point have been installed on the gas 

line to the humidifier. 

9.  Confirm that gas is supplied to the humidifier and that the shut-off valve located 

outside the humidifier is closed. 
Once the shut-off valve is turned ON, check for leaks, gas, smell or hissing 
sounds. 

 

Flue Gases 

Venting 

10.  Verify the flue gases venting as follows: 

 

a)  A tee is installed with a drain tee cap for the condensate. 

 

b)  Check that all connections are air tight. 

 

c)  The total length of the vent equivalent is not longer than 100ft (30m). 

 

d)  An approved venting system is used, such as one of the following: 

 

Cheminee Lining HEP, HEPL or HEPL2 rigid venting system, or 

 

Flexmaster Z-Vent Model SVE Series III rigid venting system, or 

 

DuraVent FasNSeal (single-wall) or FasNSeal W2 (double-wall) 
venting system, or 

 

Magnaflex’s PV model insulated flexible venting system, or 

 

Selkirk/HeatFab Saf-T Vent Model single-wall or double-wall venting 
system, or 

 

Other system, please specify (for reference) __________________ 
_____________________________________________________ 

 

Note: 

Aluminum B vent is not acceptable. 

 

Controls 

11.  Ensure  that a  high  limit  duct  humidistat  is  installed, properly  connected  to the 

humidifier and that the setpoint is properly adjusted. 

 

12.  Verify that a room or return air duct humidistat is installed, properly connected 

to the humidifier and that the setpoint is properly adjusted. 

 

13.  Turn the power ON at the disconnect switch. 

 

14.  Confirm  the  control  set-up  of  the  humidifier  (display  #200).  The  humidifier  is 

factory  set  with  EXTERNAL  control  set-up,  which  means  that  the  humidity 
demand is controlled by the room or duct humidistat. 

 

15.  Ensure that the type of signal (0-10Vdc, 2-10Vdc or 4-20mA) of the humidistat 

corresponds  to  the  type  set  in  the  humidifier  control  set-up  menu  (display  # 
201). 

 

!