NATIONAL AIR

VIBRATOR CO.

®

BH Vibrator Operation, Maintenance, and Troubleshooting 

Air Control Connection:

1.  Install air control package (Figure 1).
2. 

Blow out air line to flush contaminants before 

connecting the vibrator.

3. 

Fill the lubricator with recommended lubricant or oil 

(see Lubrication Recommendation Bulletin 4000.503).

4.  Open valve.
5.  Set the pressure regulator to 50 PSI (see FRL 

instructions).

6. 

Adjust the lubricator to recommended setting (see 

Lubrication Recommendation Bulletin 4000.503).

7. 

Adjust air regulator to the lowest pressure that will 

give the desired material flow performance, NOT to 

exceed 60 PSI.

Installation Note: 

All vibrators must be installed with a filter, 

regulator, and lubricator (FRL).

Maintenance:

1. 

Check lubricator and fill with recommended oil type if 

level is low (see Lubrication Recommendation Bulletin 

4000.503).

2. 

Check that air pressure is correctly set for 

most efficient operation. Drain filter to remove 

contaminants (water, scale, etc).

3. 

Check all air connections and tighten if necessary.

4.  Torque all bolts that may have been loosened over a 

period of time (maintenance/plant-shutdown).

5.  Be certain vibrator is well lubricated at all times. One 

way to check this is to place hand over exhaust while 

running. A fine film of oil on the palm of the hand will 

confirm that the vibrator is being lubricated properly.

Figure 1 (Air inlet located on top headplate for single impact 

BH models)

Mounting With Channel Mounting:

Note: Use channel mounting plate (See Figure 2). Safety cable 

recommended.

1. 

Determine proper mounting location. Assure a 

mounting angle greater than 20° unless an internal 

spring is installed.

2. 

Skip-weld reinforcing bars to hopper. Do not weld 

corners. 

3. 

Skip-weld both channel legs to reinforcing bars. Do not 

weld corners. 

4.  Install vibrator and mounting bolts.
5.  Install lock washer (if included) and nut. Torque 

mounting hardware to recommended specification. 

(See Bin Hopper (BH) Vibrator Operation Manual)

6. 

Re-torque mounting hardware after 24 hours of 

equipment operation.

Figure 3

Figure 2

Mounting With T-Slot Mounting Plate:

Note: Use T-slotted mounting plate (See Figure 3). Safety 

cable recommended.

1. 

Determine proper mounting location. Assure a 

mounting angle greater than 20°, unless internal 

spring is installed. 

2. 

Skip-weld reinforcing plate to hopper. Do not weld 

corners. 

3. 

Skip weld t-slot to reinforcing plate. Do not weld 

corners. 

4.  Insert bolts in slots and position vibrator onto t-slot.
5.  Install lock washer and nut. Torque mounting 

hardware to recommended specification. (See Bin 

Hopper (BH) Vibrator Operation Manual)

6. 

Re-torque mounting hardware after 24 hours of 

equipment operation.