 SLE-LTEVI-FIRE & SLE-LTEAI-FIRE Commercial Series Dual-Path Alarm Communicators -- Installation Instructions 

ble  signal  shall  be  sent  to  Central  Station  within  5 

minutes of failure by the remained active channel. 

d.  Reliability of the signal shall be achieved by any of the 

following: 

 

Signal  repetition  -  multiple  transmissions  repeating 

the same signal 

 

Parity check - a mathematically check sum algorithm 

of a digital message that verifies correlation between 

transmitted and received message 

 

An  equivalent  means  that  provides  a  certainty  of 

99.99 percent that the received message is identical 

to the transmitted message 

e.  The  maximum  duration  between  the  initiation  of  an 

alarm signal at the protected premises, transmission of 

the  signal,  and  subsequent  display  and  recording  of 

the alarm signal at the Central Station shall not exceed 

90 seconds 

f.  A spare Central Station Receiver shall be provided at 

the  Central  Station  and  shall  be  able  to  be  switched 

into  the  place  of  a  failed  unit  within  30  seconds  after 

detection of failure 

g.  All  applicable  requirements  of  Federal  Communica-

tions Commission (FCC) shall be complied with. 

3.  When used DACT for Central Station communication, two 

means  of  communication  are  required.    The  primary 

channel shall be telephone line.  Cellular or internet com-

munication  shall  be  limited  for  the  secondary  means  of 

communication  and  comply  with  26.6.3  NFPA  72,  2010 

edition.  Another telephone line also may be used as sec-

ondary mean of communication. 

4.  The above-referenced equipment shall be used only with 

listed  fire  alarm  control  panels  and  devices,  with  which 

the compatibility has been determined by UL Listing Re-

port  

5.  Only enclosures painted red in color shall be used. 

6.  Underwriters  Laboratories  Inc.'s  listing  requirements  and 

limitations shall be complied with. 

on  site  during  any  reprogramming  of  the  radio  or  control 

panel  and  must  perform  /  re-perform  acceptance  testing.  

To perform a download or update the radio firmware, jump-

er 1 must be removed.  UL requires that the jumper be re-

placed after the download is complete.  

Failure  to  replace 

the jumper would allow downloads to the radio without 

a technician on-site

.   

 

  For  Residential  installations  jumper  1  may  be  removed  to 

permit uploading and downloading without a technician on 

site,  however,  the  dealer  is  responsible  for  ensuring  the 

system  is  operating  correctly  after  any  downloads  or 

changes to the system. 

 

NYC Fire Department Requirements  

 

1.  All uses, configurations, arrangements and functions, appli-

cations and installations shall comply with the provisions of 

New  York  City  Construction  Codes,  specifically  Building 

Code Chapter 9 & 1RCNY §3616-04.  Further, the installa-

tion  shall  be  in  accordance  with  applicable  provisions  of 

New  York  City  Fire  Code,  New  York  City  Electrical  Code, 

manufacturer's  installation requirements,  and  UL  Standard 

864. 

2.  When used Dual Path LTE Communicator (IP and Cellular) 

for  Central  Station  communication  both  primary  and  sec-

ondary  channels  of  communication  shall  be  required  and 

shall  meet  the  conditions  of  4.1  –  4.7.    IP  communication 

shall  be  used  as  primary  channel  of  communication  with 

Central  Station  and  Cellular  Communicator  shall  be  used 

as  the  secondary  channel  of  communication  or  in  reverse 

order:  Cellular Communicator as primary and Internet con-

nection as the secondary channel. 

a.  Each  communication  channel  shall  be  monitored  for 

integrity at intervals not exceeding 24 hours. 

b.  Failure any channel of communication shall be annunci-

ated  at  the  protected  premises  within  5  minutes  of  fail-

ure. 

c.  When any channel of communication has failed, a trou-

Содержание StarLink SLE-LTEVI-FIRE

Страница 1: ...icators are for use as the primary means of communication with the central station and do not have backup mode capability Dual Path Communicators can also be utilized as a Sole Path Cell Communicator...

Страница 2: ...acts TB6 IN 2 See TB5 above TB7 IN 3 Fire Alarm input Wire to FACP Fire Alarm relay N O with parallel 10K EOLR at FACP TB8 IN 3 See TB5 and TB7 above Secondary Telephone RJ 45 socket for FACP DACT con...

Страница 3: ...is blinking in any other manner please contact technical support GREEN IP NETWORK CONNECTION LED Labeled D14 or DS14 this LED is located to the right of the ETHERNET socket on the PC board Operation i...

Страница 4: ...ed at the lower right corner of the PC board The radio tower signal strength may fluctuate from day to day therefore it is best to try to find a mounting location where the LED pro vides a minimum of...

Страница 5: ...AT THE NOC NOC Originated Alarms Contact ID Event Data Sent Pulse Format Event Code Sent Initiated By Comments Supervisory Fail E356 A00 Zn000 99 Automatically by NOC if fail to receive any signal fr...

Страница 6: ...ext regular supervision transmission will occur at the interval deter mined by your rate plan Configuration Download Firmware Updates Technician on site required For Commercial Installations a technic...

Страница 7: ...olor shall be used 6 Underwriters Laboratories Inc s listing requirements and limitations shall be complied with on site during any reprogramming of the radio or control panel and must perform re perf...

Страница 8: ...connections are power limited except AC Mains and battery terminals JP1 Shunt JP1 on top 2 pins Optional Use 12 or 24VDC Listed regulated power supply Note Common radio ground and FACP ground GREEN RE...

Страница 9: ...io STARLINK RADIO HOUSING StarLink Radio Terminals PC Board All connections are power limited except AC Mains and battery terminals Optional Use 12 or 24VDC Listed regulated power supply Note Common r...

Страница 10: ...ry terminals JP1 Shunt JP1 on top 2 pins Wiring Diagram for FACP Relay Trigger Input Reporting Refer to section SUPPLYING POWER NC NORMALLY ENERGIZED FIRE TROUBLE RELAY C NO 10k Aux Power Regulated 12...

Страница 11: ...d and FACP monitors TELCO 2 Program only TELCO 1 supervision Note Connect IN2 to a panel output used for identifying Telco line cut this is the DACT interconnect wiring to the radio PC Board All conne...

Страница 12: ...12 StarLink SLE LTEVI FIRE SLE LTEAI FIRE Commercial Series Dual Path Alarm Communicators Installation Instructions This page intentionally left blank...

Страница 13: ...StarLink SLE LTEVI FIRE SLE LTEAI FIRE Commercial Series Dual Path Alarm Communicators Installation Instructions 13 Housing Template 1 1 Scale Three Gang Mounting Double Gang...

Страница 14: ...14 StarLink SLE LTEVI FIRE SLE LTEAI FIRE Commercial Series Dual Path Alarm Communicators Installation Instructions This page intentionally left blank...

Страница 15: ...and firmly secure the conductors to the pigtail using an ap propriate wire nut or crimp connector for the num ber and gauge of conductors used IMPORTANT WIRING METHODS Incorrect Correct Use pigtail a...

Страница 16: ...ncelled NAPCO neither assumes nor authorizes any other person purporting to act on its behalf to modify to change or to assume for it any other warranty or liability concerning its products In no even...

Отзывы: