Remote Operator Interface provides a browser-based dashboard for commissioning
agents and engineers to access metering and relay telemetry, as well as relay event
information quickly and early without the need for any special software or skillset.
This feature does not interfere with any third-party monitoring or SCADA and may
be disabled (or upgraded) by the customer at any time.
Networking Communications All configurations of the myPV ClearSky are
equipped with an unmanaged 8-Port 10/100BaseT(X) Fast Ethernet switch. All
equipment mentioned above is connected to and IP addressed for networking
communication through this switch by default. (Additional standard options available
below)
Self-Powered & Battery Backed-Up All controls, networking, metering, and
relaying equipment run on a self-contained 24V, 20A power supply that includes
battery backup. In the event of loss-of-grid, the system remains fully operational to
provide telemetry, trip event information and alarming.
IEEE 386 MV Interfaces All configurations of the myPV ClearSky use industry
standard bushing well and inserts MV interfaces. 200A load-break or 600A dead-
break interfaces may be specified at the time of ordering based on facility amperage
requirements. (Additional standard options available below)
Standard Options
The myPV ClearSky Interconnection product line provides standard options to upgrade
and add components in a manner that supports the most frequently requested customer
requests.
Standard Options Include
Revenue Grade Metering Upgrades
[DEFAULT] Basic PQ waveform recording (15th harmonic, 16 samples/cycle, 15 cycle
duration)
[UPGRADE] Advanced PQ waveform recording (63rd harmonic, 16/128/256
sample/cycle, 15-600 cycle duration)
Protection Relay Upgrades
Содержание ClearSky
Страница 1: ...myPV ClearSky User Manual 1 myPV ClearSky User Manual ...
Страница 12: ...Resources 12 ...
Страница 14: ...Resources 14 ...
Страница 19: ...Resources 19 ...
Страница 20: ...Resources 20 ...
Страница 48: ...Pre Energization Checks 48 Control Panel Verification Locations ...
Страница 55: ...Initial Energization 55 ...
Страница 63: ...Operational Testing 63 The myPV ClearSky may be left in this condition indefinitely ...
Страница 64: ...Operational Testing 64 Numbered Illustration of Mode Selection Switch Protective Relay Indicators ...
Страница 68: ...Spare Parts 68 ...
Страница 69: ...Spare Parts 69 ...