Page 4 of 10
AR81.8
CONTEMPORARY WATER COOLERS
I N S TA L L AT I O N / M A I N T E N A N C E I N S T R U C T I O N S
ELECTRIC DRINKING FOUNTAIN
Date:
04/20/2021
7020-998-001
MURDOCK MFG. •
15125 Proctor Avenue • City of Industry, CA 91746 USA
Phone 800-453-7465 or 626-333-2543 • Fax 626-855-4860 • www.murdockmfg.com
Member of
6. Position the top of the Fountain assembly over the Frame S-clip just below the Chiller basepan and engage
while securing bottom tabs to Frame assembly with #10-32 screws and washers provided. Scews must
thread into captive nuts behind Frame tab. Tighten screws to pull the Fountain flush with the wall.
9. After thoroughly flushing supply line, connect water supply to chiller.
3.
Recheck all water and drain connections with water flowing through system.
1. Provide wall opening as indicated in Rough-in sheet. Provide structural support around opening for frame
anchoring if required.
4. Secure Frame to wall through sides top and bottom using anchoring hardware by others.
8. Make-up 1-1/4” OD waste connection.
START UP:
1.
Before assembling the upper and lower Removable Access Covers to the Fountain, but after thoroughly
flushing the supply line and connecting it to the fixture, turn on building water supply and check all
connections for leaks.
3. Insert and center mounting frame into the rough-in blockout, with sides, top and bottom flange against
finished wall. Level and secure using mounting hardware provided by the installer. Verify if level and shim if
necessary.
2.
Air within the Fountain or the structure supply piping will cause an irregular outlet stream until purged out
by incoming water.
4.
Install upper Removable Access Cover to the Fountain by sliding the Cover into the Fountain’s Mounting
Channel (DETAIL A), then secure the upper and lower Covers to the Fountain’s frame using the supplied
#8-32 screws & washers (Illustrated Below).
5. Place the Chiller Unit onto the basepan of the frame assembly. Make up electrical connections as required.
Refer to A910.8 Chiller manual 7020-978-001 for complete Chiller installation information.
2. Carefully remove Drinking Fountain and Chiller mounting frame from packaging to prevent damage.
7. Make up supply connections to 3/8” OD Tube x 1/4” OD Tube Y-Strainer Chiller and riser connections from
Chiller to Fountain. Riser 1/4” OD tube from Chiller to Fountain should be insulated to prevent condensation
and maintain cool water temperature. Refer to Water Path and Chiller detail.
INSTALLATION STEPS: (ILLUSTRATED ON FOLLOWING PAGES)
DETAIL A
A
Upper Access Cover
Fountain Frame Assembly
#8-32 Screws (Provided)
2
1
3
1
2
3
Mounting Channel
4
4