26
10. The ground bar must be drilled, then attached to the module
ground lug.
11. Reinstall the buss duct and isolation switch covers. Install
the main power connectors as shown.
NOTE: IT IS THE ELECTRICIAN’S RESPONSIBILITY TO CONNECT
MAIN POWER TO THIS CONNECTOR.
12. Install the power phase monitor as shown. When correctly
installed the lettering on the power phase monitor is inverted.
Wires are run to the normally open contact of the power phase
monitor and connect to the master control.
DANGER:
To avoid the risk of electrical shock, personal injury or death, disconnect all electrical power to the unit before performing any maintenance
or service. The unit may have more than one electrical power supply. Assume all electrical wires are live, energized wires. Use lockout/tagouts.
Module wiring connections to the power junction
box must be completed by a qualified electrician.
NOTE:
Be sure to replace all protective covers
after completing wiring connections.
On water cooled chillers with single point power, optional wire whips may be ordered and
substituted for the standard buss bar. The conduit, wiring and junction box are shipped as part
of the loose parts package. The wire and conduit are then connected to the junction box as the
modules are installed. Each wire and circuit breaker is marked for correct connection.
Single Point Power
Each wire and circuit breaker is marked for correct
connection.