Chapter 12 FRU Replacement Procedures
Gen 3 Site Controller System Manual
Site Controller Replacement
12-4
68P80801E30-A 5/1/2002
Installation
Install Site Controller in Equipment Cabinet as follows:
1.
If adding a Site Controller, install side rails in the appropriate Site
Controller mounting position in the rack.
2.
While supporting the Site Controller, slide the Site Controller in the
Equipment Cabinet mounting position.
3.
Secure the Site Controller to the Equipment Cabinet mounting rails
using the four M6 TORX screws. Tighten the screws to 4.5 N-m (40
in-lb).
4.
Connect the green/yellow ground conductor between the secondary
ground bar and the grounding lug on the rear of the housing, and
ensure the connection is tight.
5.
Connect cabling to the Site Controller rear panel connectors as
tagged during the Site Controller removal. If adding a Site
Controller, perform required cabling in accordance with Appendix C
- Cabling Diagrams.
6.
Perform the Site Controller verification in accordance with the "Site
Controller Setup/ Verification" section of Chapter 6 - System
Download/ Testing.