background image

TYPICAL EQUIPMENT ROOM FLOOR PLAN LAYOUT

Open 

Drain Pipe

Closed 

Vented

Drain

OR

1

2

2 Inch Exhaust 

for Top Pump 

Connection

2 Inch 

Pipe for 

Addition of 

Exhaust Vent 

Assembly. 

See Note c.

Notes:  See Installation Note J below for required pipe material.

a.  All piping and fittings must be 4-inch instead of 3-inch 

when preparing the site for a 3 pump installation.

b.  Use a second dual 45° Y fitting configuration when 

preparing the site for a 4-pump installation.

c.  Pipe required for the installation of the Exhaust Vent 

Assembly supplied with each pump.  See exhaust 

ventilation requirements provided on the back cover.

Top 3 Inch 

45° Y

48"

4"

4"

107"

20"

24"

Sewer Drain

12"

4"

4"

80"

Pump/Tank

Connection Manifold 

MT10 or CT20 

Tank

 

Single  or 

Stacked Pumps

(V3, V5 or V7)

23"

Single  or 

Stacked Pumps

(V3, V5 or V7)

76"

62"

1"

12"

24"

4"

B

A

A

D

E

J

H

K

C

INSTALLATION NOTES:

G

F

A. PUMP INSTALLATION SPACE - Area for stacked or side by side pump installation. Keep 4 inch space from walls.  Only stack up to 2 pumps in one area.  

B. TANK INSTALLATION SPACE - Area for typical side by side tank installation. Keep 4 inch space from walls. Never install the CT20 / CT22 tank on top of a pump.

C. SEWER DRAIN - Provide a drain for the removal of waste liquids from the MOJAVE tank.  Use an open drain pipe (

1

 

½

 inch P-Trap with 1 inch air gap or 

floor sink) or a closed vented drain.  See detail 1.

D. TANK WASHOUT - Provide a water source terminated with a 

½

” 

inch FNPT shut-off valve providing water pressure between 20 and 100 psi for daily tank 

washout.  Valve location must be no more than 10 feet from the tank installation to allow connection of supplied 10-foot 3/8-inch Poly tubing to the tank 

washout port.  Provisions for backflow prevention may be required.  Check local code requirements.

E. MASTER CONTROLLER ELECTRIC OUTLET - Master Controller requires a dedicated standalone 120V, 5 AMP or 220V, 5 AMP grounded receptacle.  

F. PUMP ELECTRIC SERVICE -  Each Mojave pump is wired directly with a dedicated 220V, 20 AMP, single phase 60 Hz circuit.  If Main Circuit panel is not 

located in equipment room, a disconnect box with approved ground is needed for each pump.  Disconnect boxes should be mounted no more than 3 feet 

of each other and 3 feet of installation center line.

G. SUB FLOOR INSTALLATION VACUUM LINE - See Plumbing Requirements for connection to tank input via supplied hose.

H. OVERHEAD INSTALLATION VACUUM LINE - See Plumbing Requirements for connection to tank input via supplied hose.

J. HEAT EXHAUST - See Plumbing Requirements for the exhaust vent line required for specific Mojave configurations. Use metal pipe on systems whenever the 

Heat Exchanger is removed. Schedule 40 pipe can normally be used on typical Mojave configuration installations with a Heat Exchanger.  When installing two 

pumps, a reducing Y adapter (shown by detail 2 above) is needed to connect both vent tubes to a common 3-inch exhaust vent line.

K. PUMP/TANK MANIFOLD - User fabricated to connect 3 or 4 pumps to a tank. Used with 3V5 and 4V5 systems.  See Pump/Tank Connection Manifold.

3

Inch

2 Inch Pipe for Addition 

of Exhaust Vent 

Assembly. See Note c.

Содержание V3

Страница 1: ..._____________________ Phone __________________________________________________ Dealer __________________________________________________ Dealer Address __________________________________________________ All installations must conform to local codes All pumps comply with NFPA 99C level 3 requirements System being installed AS CHECKED q V3 q V5 q V7 q 2V3 q 2V3CT q 2V5 q 2V5CT q 2V7 q 3V5 q 4V5 ...

Страница 2: ...aust to Outside Vent V3 V5 or V7 Vacuum Pump Heat Exchanger Gate Valve Check Valve Sewer Drain MT10 Separator Tank Gas Typical MOJAVE System Installation Liquids Solids System Components V3 V5 V7 2V3 2V3CT 2V5 2V5CT 2V7 3V5 4V5 V3 Pump Assembly 1 0 0 2 2 0 0 0 0 0 V5 Pump Assembly 0 1 0 0 0 2 2 0 3 4 V7 Pump Assembly 0 0 1 0 0 0 0 2 0 0 MT10 MT12 Tank Assembly 1 1 1 1 0 1 0 0 0 0 CT20 CT22 Tank As...

Страница 3: ... in 28 cm 13 5 in 34 cm 3 in 8 cm V3 V5 and V7 Vacuum Pump Dimensions 17 in 43 cm 25 in 64 cm 21 in 53 cm 17 5 in 44 cm 2V3 or 2V5 System Installation Recommended Stacked Pumps with Tank on Side 33 in 84 cm 34 in 86 cm V3 V5 and V7 System Dimensions 23 in 58 cm 50 in 127 cm 2V7 2V3CT or 2V5CT System Installation Recommended Stacked Pumps with CT20 CT22 Tank on Side 34 in 86 cm 50 in 127 cm MT10 MT...

Страница 4: ... Height from Riser Trap to Main Line OVERHEAD INSTALLATION Alternate system installation layout should be used only when unable to use the sub floor plumbing layout Ceiling Junction Box See Note 2 1 2 Inch Diameter Riser Minimum Slope 1 4 inch per 10 Feet Main Line Riser for connection to tank input See Note 1 MAIN LINE See Notes 2 3 4 Junction Box See Note 2 MAIN LINE See Notes 2 3 4 5 CONNECTOR ...

Страница 5: ...ng water pressure between 20 and 100 psi for daily tank washout Valve location must be no more than 10 feet from the tank installation to allow connection of supplied 10 foot 3 8 inch Poly tubing to the tank washout port Provisions for backflow prevention may be required Check local code requirements E MASTER CONTROLLER ELECTRIC OUTLET Master Controller requires a dedicated standalone 120V 5 AMP o...

Страница 6: ... PVC Sch 40 2 PVC Sch 40 One 3 or two 2 PVC Sch 40 One 3 or two 2 PVC Sch 40 One 3 or two 2 PVC Sch 40 One 4 or three 2 PVC Sch 40 Two 3 or four 2 PVC Sch 40 Exhaust Vent Pipe Not Using Heat Exchanger See note 1 2 Metal Pipe 2 Metal Pipe 2 Metal Pipe One 3 or two 2 Metal Pipe One 3 or two 2 Metal Pipe One 3 or two 2 Metal Pipe One 4 or three 2 Metal Pipe Two 3 or four 2 Metal Pipe Minimum Suction ...

Страница 7: ...rizontal to Floor 3 PVC or Copper Clean out Plug Used with P N MIK4 Supplied by Plumber Air F l o w 2 PVC or Copper Tubing for Tank Hose Supplied by Plumber Check Valve Side View CT20 TANK INLET CONNECTION DETAIL 6 inch Riser Customer Supplied Tee Connector 3 4 FNPT 2 Flexible Coupling Connector 1 4 inch Vacuum Sample Port to Master Controller Reducing Bushing Swivel Elbow 2 Pipe for connection to...

Страница 8: ...ush Elbow 35 18 Exhaust Vent Protection If the exhaust piping is venting to the outside of the building precautions must be taken to protect the equipment room from weather elements and animal intrusion This can be accomplished by using one of the three methods shown on the right Wall Mounted Outside Vent Protection Shroud Screen Roof Mounted Outside Vent Protection Shroud Screen Screen Exhaust Ve...