35
(2)Water flow rate adjustment operation (when the secondary side control is disabled)
Checking the flow rate after the flow rate adjustment operation
The flow rate adjustment operation adjusts the pump output and water flow rate valve opening to determine how to
match the flow rate characteristic to the local circuit.
Use the method below (*3
1
to
4
) to check the operation
result (characteristic).
If air bleeding was not done fully and the map not created properly, a water shutoff error, high pressure
error or other problems will occur when operating the system. Check the points below in this case. If the
values are abnormal, redo the air bleeding and flow rate adjustment operations.
(*3)
1
Set the PCB’s DIP switches as shown below.
2
Press SWP3 repeatedly to change the code shown in the PCB’s display. The code changes with each
press (*4).
Continue pressing SWP3 until ‘dxx’ is displayed in the PCB’s digital display.
(‘dxx’ is a code that stores the flow rate for a given pump output opening and valve opening. See Table 1.)
(*4) If the flow rate adjustment operation has never been performed, ‘ng’ appears after the system startup
operation. Perform the flow rate adjustment operation in this case.
Step
Contents
Operation and check points
Supplemental explanation
a
Water level check
Check the water level is neither at the full or
empty level.
Water is supplied even when the target water level
has been reached.
b
Power operation
Turn the power ON.
If the startup operation has not finished, SW2-9
and SW2-3 need to be set as a stopgap measure
(see Note 1).
If this flow rate adjustment operation has never
been performed ‘--ng’ is displayed.
c
Operation
procedure
Change the setting of PCB slide SWS1 from
REMOTE to LOCAL.
* Make sure SWS2 is set to the lower side. (See
page 23.)
d
Operation
procedure
Change the setting of SW1-6 from OFF to ON.
* Step c and Step d must be taken in sequence to
run the flow-adjustment operation.
* The pump operation and flow rate adjustment
valve opening are automatically adjusted, and
the flow rate is measured in 30 second intervals.
* You can check whether this flow rate adjustment
operation has ended or is underway using the
setting given in Note 2.
e
Stop operation 1
Change the setting of SW1-6 from ON to OFF.
-
f
Stop operation 2
Change the setting of PCB slide SWS1 from
LOCAL to REMOTE.
-
SW2
SW3
-10
-5
-6
-7
-8
-9
-10
OFF
OFF
OFF
OFF
OFF
ON
ON
WT08219X05.book 35 ページ 2018年10月1日 月曜日 午後7時47分