VIII
Troubleshooting ]
- 97 -
HWE09070
GB
[4] Servicing the WCB
1. Service
panel
2. Control
box
3. Thermistor (liquid pipe/gas pipe temperature detection)
*Special care must be taken when replacing heavy parts.
Work procedure
Explanatory figure
1) Remove the two lock nuts on the control box, loosen the
other two, and remove the control box.
2) Remove the three fixing screws on the service panel,
and remove the service panel.
3) Remove the nine machine screws on the ceiling panel,
and remove the ceiling panel.
Work procedure
Explanatory figure
(1) To check the inside of the control box, remove the
two lock nuts on the control box cover.
1) Check the terminal connection of the power wire or of
the transmission line.
2) Check the transformer.
3) Check the address switch.
(2) When the control board is replaced, the followings
must be noted.
(1) Check that the board is for use with WCB.
(2) Check that the wire and the connector are properly con-
nected.
It is not required to remove the two fixing screws on the
control box when checking the inside.
*Special care must be taken when replacing heavy parts.
Work procedure
Explanatory figure
(1) Remove the service panel.
1) Check TH15 according to the procedure in section 1. 1),
2).
2) Check TH11, TH12, TH13, TH14, and TH16 according
to the procedure in section 1. 1), 2), 3).
(2) Remove the lead wire of the piping sensor from the
control board.
1) TH11,TH12,TH13, TH14 (CN10)
2) TH15,TH16 (CN11)
(3) Pull out the temperature sensor from the tempera-
ture sensor housing, and replace the temperature
sensor with the new one.
(4) Connect the lead wire of the temperature sensor se-
curely on the control board.
Loosen
Service panel
Control Box
Ceiling panel
TH13
TH11
TH15
TH14
TH16
TH12
Содержание CMB-PW202V-J
Страница 1: ...Service Handbook AIR CONDITIONERS MODEL CMB PW202V J ...
Страница 9: ...HWE09070 GB ...
Страница 11: ... 2 ...
Страница 25: ... 16 ...
Страница 28: ... II Restrictions 19 HWE09070 GB ...
Страница 31: ... 22 II Restrictions GB HWE09070 ...
Страница 36: ... 27 HWE09070 GB III WCB Components 1 WCB Components 29 2 Control Box of the WCB 30 3 WCB Circuit Board 31 ...
Страница 37: ... 28 ...
Страница 40: ... III WCB Components 31 HWE09070 GB 3 WCB Circuit Board SW1 SW2 SW5 SW6 SW4 ...
Страница 41: ... 32 III WCB Components GB HWE09070 ...
Страница 42: ... 33 HWE09070 GB IV Electrical Wiring Diagram 1 Electrical Wiring Diagram of the WCB 35 ...
Страница 43: ... 34 ...
Страница 45: ... 36 IV Electrical Wiring Diagram GB HWE09070 ...
Страница 46: ... 37 HWE09070 GB V Refrigerant Circuit 1 Refrigerant Circuit Diagram 39 2 Principal Parts and Functions 40 ...
Страница 47: ... 38 ...
Страница 51: ... 42 ...
Страница 61: ... 52 VI Control GB HWE09070 ...
Страница 63: ... 54 ...
Страница 73: ... 64 ...
Страница 108: ... 99 HWE09070 GB IX LED Monitor Display on the Outdoor Unit Board 1 How to Read the LED on the Service Monitor 101 ...
Страница 109: ... 100 ...