5.3
Assembly
5.3.1
Safety instructions
WARNING
The vessel may turn over during mounting.
Securing the vessel against tipping is imperative.
Use an appropriate lifting jack.
WARNING
Warning of hazardous area and/or personal injury
The locking washers of the constrainers may only be used once.
Insert new washers in case they have been damaged or removed. Spare parts, see
Chapter
NOTICE
Welding or lightning strike current flowing through the cell can damage it.
All electrical welding on the weighing system must be finished before mounting the load
cells.
When installing the load cell, immediately bypass the load cell with the flexible
copper strap provided for this purpose (included in the equipment supplied, see
Chapter
During any additional electrical welding work near the load cell:
-
Disconnect the load cell cables.
-
Bypass the load cell using the flexible copper strap.
-
Make sure that the grounding clamp of the welding set is fitted as closely as possible
to the welding joint.
5.3.2
Installing the mounting kit and inserting the load cell
Note:
Screw mounting of the upper and lower plates is described below.
The operations must be performed at all supporting points (e.g., vessel) of the weighing
object.
Requirements:
-
All threaded holes for the upper plate are available in the vessel lug/vessel foot (see
Chapter
).
-
The lift-off protection is in the upper position.
Mounting kits PR 95T/00, ../01, ../10, ../11
5 Installation
EN-18
Minebea Intec