MCAC-ATSM-2014-09 R410a tropical air-cooled scroll chiller unit 60Hz
Installation 131
.
Installation steps of the damper
Step
Content
1
Make sure that the flatness of the concrete foundation is within ±3mm, and then place the unit on the
cushion block.
2
Raise the unit to the height suitable for installation of the damping device. Remove the clamp nuts of the
damper.
3
Place the unit on the damper, and align the fixing bolt holes of the damper with the fixing holes on the unit
base.
4
Return the clamp nuts of the damper to the fixing holes on the unit base, and tighten them into the damper.
5
Adjust the operational height of the damper base, and screw down the leveling bolts. Tighten the bolts by
one circle to ensure equal height adjustment variance of the damper.
6
The lock bolts can be tightened after the correct operational height is reached.
2. Water System Installation
Notice:
●
After the unit is in place, chilled water pipes can be laid.
●
The relevant installation regulations should be abided with when conducting connection of water pipes.
●
The pipelines should be free of any impurity, and all chilled water pipes must conform to local rules and
regulations of pipeline engineering.
2.1 Basic requirements of connection of chilled water pipes
No.
Content
1
All chilled water pipelines should be thoroughly flushed, to be free of any impurity, before the unit is operated.
Any impurity should not be flushed to or into the heat exchanger.
2
Water must enter the heat exchanger through the inlet; otherwise the performance of the unit will decline.
3
The inlet pipe of the evaporator must be provided with a target flow controller, to realize flow-break protection
for the unit. Both ends of the target flow controller must be supplied with horizontal straight pipe sections whose
diameter is 5 times that of the inlet pipe. The target flow controller must be installed in strict accordance with
“Installation & Regulation Guide for Target Flow Controller”. The wires of the target flow controller should be led
to the electric cabinet through shielded cable. The working pressure of the target flow controller is 1.0MPa, and
its interface is 1 inch in diameter. After the pipelines are installed, the target flow controller will be set properly
according to the rated water flow of the unit.
Содержание MGBT-D25W/DN1
Страница 33: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 33 4 2 MGBT F60W DN1...
Страница 34: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09 4 3 MGBT F120W DN1...
Страница 35: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 35 4 4 MGBT F180W DN1...
Страница 37: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 37 5 2 MGBT F60W DN1...
Страница 38: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09 5 3 MGBT F120W DN1...
Страница 39: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 39 5 4MGBT F180W DN1...
Страница 40: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09 6 Expolde view 6 1 MGBT F25W DN1...
Страница 47: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 47...
Страница 50: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09...
Страница 53: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 53 6 5 MGBT F60W DN1 46...
Страница 56: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09...
Страница 57: ...MCAC ATSM 2014 09 R410a tropical air cooled scroll chiller unit 60Hz Capacity tables 57 Change to this one...
Страница 60: ...R410a tropical air cooled scroll chiller unit 60Hz MCAC ATSM 2014 09 88...