Tools and equipment required
— Set of cross-head screwdrivers
— Set of slotted screwdrivers
— Torx screwdriver TX10
— Torx screwdriver TX20
4
Dismantling the ventilation unit
4.1
Detach electrical connections and uninstall the ventilation unit
DANGER
Potentially fatal voltages
—
Only qualified electricians may work on the electrical installation.
— The VDE regulations or any special safety regulations applicable in your country
apply to the electrical installation work.
►
Before starting to uninstall, disconnect the mains cable and the control cable (if
used) on all poles from the main power supply.
► Observe the five safety rules (DIN VDE 0105-100, EN 50110-1) for working on elec
-
trical systems:
— Disconnect from mains (all-pole disconnection of a system from live parts)
— Secure against reconnection
— Check that the system is voltage-free
— Earth and short-circuit
—
Cover or block off access to adjacent live parts
►
Detach the electrical connections from the ventilation unit.
►
Uninstall the ventilation unit from its installation location.
►
Place the ventilation unit on a suitable work surface for the rest of the dismantling
work.