Step  7.

Check that none of the ATTN status LEDs on the spines are yellow.

Step  8.

Go around to the other side of the switch chassis and check the leaf board status 
LEDs.

Step  9.

Check that the leaf physical and data link status LEDs in the spines are lit.

Configuring the Switch for the First Time

Step  1.

Connect the host PC to the RS-232 port of the MTS3610 switch using the supplied cable.

This LED should be off.

This LED should be on.

The green connector 
LEDs should be on.

The yellow connector 
LEDs should be 

 

blinking.

Green – indicates Power OK

 ATTN – Yellow indicates fault 
in spine, normally off

Green – indicates that 
there is a physical connec-
tion to the spines through 
this link

Yellow – indicates that there 
is a logical connection to the 
spines through this link

Links A and B to each leaf

 Leaf numbers

RS-232 port

Содержание MTS3610

Страница 1: ...may have occurred during shipping Note If anything is damaged or missing contact your customer representative immediately Physical Installation Warning This equipment is very heavy Safety is the first...

Страница 2: ...edure on the MTS3610 Switch system Step 1 Put an ESD prevention wrist strap on your wrist and make sure there is good contact between your body and the strap Step 2 Plug the other end of the wrist str...

Страница 3: ...e chassis as low as possible to keep the center of gravity low Choose which way you want the chassis to face in the rack Keep in mind that one side of the chassis can have up to 324 cables connected T...

Страница 4: ...as low as possible Step 2 Insert four caged nuts into the rack on the side you plan to have the connectors Note the U number on the rack Figure 4 Caged Nut Insertion Step 3 Screw the rail slides onto...

Страница 5: ...echanical lifting device Figure 7 Mechanical Lifting Device Step 3 Raise the chassis 2 cm 1 above the level of the shelf Step 4 Move the chassis over the shelf Place the chassis so that the face plate...

Страница 6: ...en all ten bolts and nuts Step 10 Place the lock down bar over the lip of the chassis and align the holes in the lock down bar with the holes in the shelf Figure 9 Lock Down Bar Step 11 Place a washer...

Страница 7: ...not rely on the PSU grounds It is absolutely necessary to connect the grounding post Make sure the connections are solid and permanent Figure 10 Ground Connection Installing the Cable Holder Holes fo...

Страница 8: ...the remaining power supply units Note A fully loaded MTS3610 switch system can draw 5 2 kW of power Make sure that the outlets and circuits will not be overloaded Spread out the load over at least two...

Страница 9: ...or the First Time Step 1 Connect the host PC to the RS 232 port of the MTS3610 switch using the supplied cable This LED should be off This LED should be on The green connector LEDs should be on The ye...

Страница 10: ...omments Do you want to use the wizard for initial configuration You must perform this configuration the first time you operate the switch or after resetting the switch to the factory defaults Type y a...

Страница 11: ...RX mcast packets 0 RX discards 0 RX errors 0 RX overruns 0 RX frame 0 TX bytes 122850 TX packets 1119 TX discards 0 TX errors 0 TX overruns 0 TX carrier 0 You have entered the following information 1...

Страница 12: ...the Switch for the First Time section Step 4 You can enter any supported command now Note For a complete reference of commands please see Mellanox FabricIT Management Software User s Manual Starting...