Mellanox Technologies Inc. 350 Oakmead Parkway, Sunnyvale, CA 94085 Tel: 408-970-3400 Fax: 408-970-3403 www.mellanox.com
MTS3610 Installation Guide
Document Number
3082
Rev 1.2.2
Package Contents
The package includes:
•
1 Chassis
•
1-18 leafs according to the amount ordered
•
18 - X leaf blanks X = the amount ordered
•
1 leaf fan module
•
1 spine fan module
•
9 spines
•
1- 2 management modules according to the amount ordered. If only 1 management module is ordered
then one MM blank will be in the package.
•
6-8 power cables depending upon your specific order
•
6-8 PSUs depending upon your specific order
•
(8 - X) PSU blanks X = the amount ordered
•
RJ45 to DB9 cable
•
1 Installation kit
•
CD
•
Installation guide
Before you install your new MTS3610 Chassis, unpack the system and check to make sure that all the parts
have been sent, check this against the parts list. Check the parts for visible damages that may have occurred
during shipping.
Note: If anything is damaged or missing, contact your customer representative immediately.
Physical Installation
Warning:
This equipment is very heavy. Safety is the first concern. The fully
loaded chassis weighs ~350 lbs (155 kg). Make sure that proper manpower and
equipment are used for transporting and moving the chassis.
Note: You will need a mechanical lift, to move and insert the chassis into the rack.
This chassis can be installed in 19” racks with a maximum depth of 81cm.
The switch platform uses 20U of rack space in a standard 19” rack. The switch ships from the factory with
mounting racks on the front side. There are four threaded connectors on the top of the chassis for connecting
eye bolts. The four eye bolts are included in the installation kit. The chassis can be lifted using these four eye
bolts and a mechanical lift. The switch is supported from underneath the unit by a shelf.
Choose a rack which is able to support the mechanical and environmental characteristics of a fully populated
switch chassis as listed in the user manual.