9763258
23 / 64
6.1
Prerequisites for assembly
6.1.1
Checking the condition at delivery
• Check that the delivery is complete immediately after receiving it by comparing
it with MEIKO’s order confirmation and/or the delivery note.
• If applicable, submit a claim for any missing parts immediately to the freight for-
warder and notify MEIKO.
• Check the machine for transportation damage.
Note
If there is any suspicion of transportation damage, the shipping company and
MEIKO must be informed immediately in writing. Photograph any damaged parts
and send the pictures to MEIKO.
6.1.2
Requirements for the installation area
The dishwashing machine is only frost-proof in as-delivered state or if equipped with
special features (optional: frost removal).
Installation of the dishwashing machine in an area where the ambient temperature is
below 0° C can result in damage to the internal water circuit components (e.g.
pump, solenoid valve, boiler, etc.).
• Ensure that the storage and installation locations are always frost free.
There is a danger of slipping in the working area due to the use of water.
• After assembly, put in place non-slip floor coverings in the working area based
on the general/location-specific safety regulations.
6.1.3
Requirements for the waste water connection
A waste water pipe is integrated into the drain pump.
• Connect the drain hose to the on-site waste water pipe.
– For Australia only:
The drain hose must be connected so that it is waterproof with a drain fitting
in accordance with AS 1589 AS 2887 and a sanitary waste water pipe or
sanitary waste water fitting in accordance with AS / NZS 1260.
• Depending on the dishwashing machine application, a grease trap may be in-
cluded, based on the general/location-specific regulations.
• Observe maximum drain heights above the finished floor.
Drain heights above the finished floor
Version
Max. drain heights
US/ UM/ ET 8.1 OS GLS UM+/ UL/ ET 8.1 (OS)
Without reverse osmosis (GiO MODULE)
700 mm
With reverse osmosis (GiO MODULE) on the rear panel
or mounted separately
420 mm (US/UM only)
540 mm (UM+/UL only)
With reverse osmosis (GiO MODULE) integrated in the
plinth
540 mm
660 mm
6.1.4
Requirements for the fresh water connection
For Australia only:
All work carried out must be in accordance with AS/NZS 3500.1!
Fresh water connections and their components must be carried out in accord-
ance with local regulations, e.g. EN 1717/DIN 1988-100. The fresh water must
be of the same quality as drinking water in microbiological terms. This also
applies to processed water.