3. First Steps
This chapter describes, how to prepare the MA Network Switch for usage.
3.1. Unpack the Device
Unpack the MA Network Switch. Remove all packing material, strips and protection films.
Keep the packing material for transport.
3.2. Install Mini-GBIC (SFP)
The MA Network Switch comes with up to four SFP cages. These cages accept mini-GBIC transceivers.
Two are at the rear panel, port 9 and 10. Two are inside the MA Switch.
To install mini-GBIC transceivers inside the switch at port 11 and port 12, call your local distributor.
Install mini-GBIC at port 9 and 10
1. Remove the mini-GBIC from its protective packaging.
Be aware of the insertion direction.
Port 9 must have the bail wire delatch on the top.
Port 10 must have the bail wire delatch at the bottom.
2. Install the mini-GBIC into the slot 9 or 10 at the rear panel, until the mini-GBIC clicks into place.
For detailed description of your mini-GBIC transceiver, refer to the transceiver manual.
Remove mini-GBIC from port 9 and 10
1. Open the ball wire delatch to disengage and remove the mini-GBIC transceiver.
2. Replace the protective plastic cover on the mini-GBIC.
The mini-GIBC is removed from the port.
3.3. Installation in a Rack
16