Pag. 46/49
Doc. ISM0076_MANUALE_CN SEAL-MV_ENG_REV04.DOCX
APPENDIX B – Startup check list
PUMP
SERIES
CN
SEAL-MV
- Do not destroying – do not modify -
Rev. N°00
Date 21/02/2013
STARTUP CHECK LIST
This document consists
of 2 pages
Nr.
Description of activity
YES /
NO /
*UPON ARRIVING CHECKS:
1
Check Pump Name Plate , Motor Name plate to tally with PO and Data Sheet
2
Any Cracks or damages to Pump or motor during shipment or handling
3
Check accessories if ordered to tally with PO
4
Are Installation, Operation and Maintenance Manuals for Pump, Motor and
Coupling supplied?
5
Have you received the Pump Curve, GA Drawing, Pump Data Sheet, Motor
Data Sheet and Wiring Diagram?
6
Have you read through and understand the IOM manuals?
*INSTALLATION CHECKS:
1
Has the Pump's baseplate being properly level and firmly secured?
2
Has the Pump and motor coupling being secured and aligned?
3
Are Suction and Discharge Pipe line with Flexible Joints being Supported and
Secured?
4
Any undue Pipe loading onto Pump inlet/Outlet Nozzle due to Mis-alignment
5
Is Suction Strainer being installed to protect the Pump?
6
Are Suction and Discharge Pressure Gauge being installed before Pump's Inlet
and Outlet?
7
Is there any Check Valve being installed at Pump's discharge Outlet?
8
Has the Power supplied for Electrical Motor being connected by qualified
electrical personnel?