Lucent Technologies Lineage
®
2000 50A Ferroresonant Rectifier J85502B-1
6 - 4 Testing
Issue 6 May 1999
4. Disconnect the rectifier's “hot” output lead from the plant
charge bus bar. Tape the loose connector.
5. Disconnect the rectifier’s ground output lead from the
charge ground bus bar. Tape the loose connector.
6. Disconnect the + and - output leads from the left side of
TB3, the rectifier ends of cables disconnected in Steps 3
and 4. Tape loose connectors.
7. Disconnect J2A from CM2 by unlatching first, then
pulling the cable connector.
8. Connect the test load to the + and - output terminals on
TB3 in the rectifier.
9. Install the regulation (REG) fuse associated with the
rectifier in the plant controller.
10. When you are ready to power the test load, you must
restore ac to the rectifier at the ac service panel, turn On
the rectifier POWER switch, and turn On the DC
OUTPUT circuit breaker. If this is initial testing, check
the control cable first (see “Preparation for Testing Off
Line”).
Preparation for
Testing Off
Line
The following steps check the plant control cable and prepare the
equipment for testing.
1. Verify that the ac supply and rectifier controls are as
shown in Table 6-A.
Caution
Support the CM2 control board when disconnecting the
cable leads or damage to the control board may result.
Do NOT disconnect plant control cable connector J2A
from control board CM2 by pulling the cable.