Chapter 9 Installation and Wiring
9-
6
(4) Mount the wire duct as it is needed.
If the clearances are less than those in Fig 9.1, follow the instructions shown below
•
If the wire duct is mounted on the upper part of the PLC, make the wiring duct
clearance 50
㎜
or less for good ventilation. Also, allow the distance enough
to press the hook in the upper part from the upper part of the PLC.
•
If the wire duct is mounted on the lower part of the PLC, make optic or coaxial
cables contact it and consider the minimum diameter of the cable.
(5) To protect the PLC from radiating noise or heat, allow 100
㎜
or more clearances
between it and parts. Left or right clearance and clearance from other device in
the left or right side should be 100
㎜
or more.
(6) MK80S has hooks for DIN rail in the base unit and expansion modules.
[ Fig 10.3 ]
High voltage
device
Other
device
100mm or more
Heat generating device
80mm
or more
80mm
or more
[ Fig 9.2 ] PLC mounting
DIN rail
Содержание MASTER-K80S
Страница 27: ...Chapter 4 Names of Parts 4 4 1 3 30 points base unit 4 1 4 40 points base unit 4 1 5 60 points base unit...
Страница 66: ...Chapter 6 Input and Output Modules 6 3 30 point base unit 4 40 point base unit DC24V DC24V DC24V...
Страница 67: ...Chapter 6 Input and Output Modules 6 5 60 point base unit DC24V DC24V...
Страница 206: ...Chapter 8 Communication Function 8 63 You can see the frame list which is designated Click OK button...