Fast commissioning / operating principle
Leuze electronic
MA 248
i
13
TNT
35/7-2
4
V
3.5
Commissioning the MA 248
i
on the PROFINET
Complete the necessary steps for commissioning a Siemens-S7 control as described
below.
Further information regarding the individual commissioning steps is provided in see chapter
12.3 "Configuration steps for a Siemens Simatic S7 control".
3.5.1
Preparing the control system
In the first step, assign an IP address to the IO Controller (S7 PLC) and prepare the control
for a consistent data transmission.
Notice!
If an S7 control is used, you need to ensure that Simatic-Manager Version 5.4 + service
pack 5 (V5.4+SP5) or higher is used.
3.5.2
Installation of the GSD file
For the subsequent configuration of the IO devices, e.g., MA 248
i
, the corresponding GSD
file must be loaded first. All data in modules required for operating the device is described
in this file. These are input and output data and device parameters for the functioning of the
device and the definition of the control and status bits.
Install the GSD file associated with the device in the PROFINET-IO Manager of your
control.