Communication manual 8400 motec PROFIBUS
Commissioning
Before initial switch-on
28
L
EDS84DMOTPBUS EN 3.0 - 11/2011
6
Commissioning
During commissioning, plant-specific data such as motor parameters, operating
parameters, responses, and parameters for fieldbus communication are defined for the
controller. Lenze devices use codes for this purpose.
The codes of the controller and for communication are saved to the memory module in a
non-volatile data set.
In addition, there are codes for diagnosing and monitoring the stations.
6.1
Before initial switch-on
Stop!
Before switching on the controller for the first time, check ...
• the entire wiring for completeness, short circuit and earth fault.
• whether the bus system is terminated through a bus terminating resistor at
the first and last physical bus station.
Содержание E84DGFCp Series
Страница 2: ...2 L EDS84DMOTPBUS EN 3 0 11 2011 ...