Vacuum Drying and Leakage Checking
101
7.
Vacuum Drying and Leakage Checking
7.1
Purpose of vacuum drying
➢
Eliminating moisture in system to prevent the phenomena of ice-blockage and copper oxidation.
Ice-blockage shall cause abnormal operation of system, while copper oxide shall damage compressor.
➢
Eliminating the non-condensable gas (air) in system to prevent the components oxidizing, pressure
fluctuation and bad heat exchange during the operation of system.
7.2
Selection of vacuum pump
➢
The ultimate vacuum degree of vacuum pump shall be -756mmHg or above.
➢
Precision of vacuum pump shall reach 0.02mmHg or above.
7.3
Operation procedure for vacuum drying
Due to different construction environment, two kinds of vacuum drying ways could be chosen, namely
ordinary vacuum drying and special vacuum drying.
7.3.1
Ordinary vacuum drying
1. When conduct first vacuum drying, connect pressure gauge to the infusing mouth of gas pipe and liquid
pipe, and keep vacuum pump running for 1hour (vacuum degree of vacuum pump shall be reached
-755mmHg).
2 If the vacuum degree of vacuum pump could not reach -755mmHg after 1 hour of drying, it indicates
that there is moisture or leakage in pipeline system and need to go on with drying for half an hour.
3 If the vacuum degree of vacuum pump still could not reach -755mmHg after 1.5 hours of drying, check
whether there is leakage source.
4 Leakage test: After the vacuum degree reaches -755mmHg, stop vacuum drying and keep the pressure
for 1 hour. If the indicator of vacuum gauge does not go up, it is qualified. If going up, it indicates that
there is moisture or leak source.
7.3.2
Special vacuum drying
The special vacuum drying method shall be adopted when:
1. Finding moisture during flushing refrigerant pipe.
2. Conducting construction on rainy day, because rain water might penetrated into pipeline.
3. Construction period is long, and rain water might penetrated into pipeline.
4. Rain water might penetrate into pipeline during construction.
Procedures of special vacuum drying are as follows:
1. Vacuum drying for 1 hour.
2. Vacuum damage, filling nitrogen to reach 0.5Kgf/cm2 .
Because nitrogen is dry gas, vacuum damage could achieve the effect of vacuum drying, but this
method could not achieve drying thoroughly when there is too much moisture. Therefore, special
attention shall be drawn to prevent the entering of water and the formation of condensate water.
3. Vacuum drying again for half an hour.
If the pressure reached -755mmHg, start to pressure leakage test. If it cannot reached the value,
repeat vacuum damage and vacuum drying again for 1 hour.
4 Leakage test: After the vacuum degree reaches -755mmHg, stop vacuum drying and keep the pressure
for 1 hour. If the indicator of vacuum gauge does not go up, it is qualified. If going up, it indicates that
there is moisture or leak source.
Содержание LICH4012021T431E-1
Страница 12: ...Service Space Indoor Units 10 3 Service Space 1000mm 1000mm 1000mm 1000m m Chart 3...
Страница 13: ...Wiring Diagrams Indoor Units 11 4 Wiring Diagrams...
Страница 15: ...Air Velocity Distributions Reference Data Indoor Units 13 36K Cooling Heating...
Страница 16: ...Air Velocity Distributions Reference Data Indoor Units 14 48 60K Cooling Heating...
Страница 21: ...Field Wiring Indoor Units 19 10 Field Wiring...
Страница 27: ...Service Space Indoor Units 25 3 Service Space Ensure enough space required for installation and maintenance...
Страница 28: ...Wiring Diagrams Indoor Units 26 4 Wiring Diagrams 12k 18k 60k...
Страница 39: ...Field Wiring Indoor Units 37 10 Field Wiring 12K 18K 60K...
Страница 43: ...Ceiling Floor Type Indoor Units 41 3 Service Space...
Страница 48: ...Ceiling Floor Type Indoor Units 46 Floor installation Discharge angle 17 Discharge angle 50...
Страница 49: ...Ceiling Floor Type Indoor Units 47 Model 36k Ceiling installation Discharge angle 17 Discharge angle 50...
Страница 50: ...Ceiling Floor Type Indoor Units 48 Floor installation Discharge angle 17 Discharge angle 50...
Страница 51: ...Ceiling Floor Type Indoor Units 49 Model 48k 60k Ceiling installation Discharge angle 17 Discharge angle 50...
Страница 52: ...Ceiling Floor Type Indoor Units 50 Floor installation Discharge angle 17 Discharge angle 50...
Страница 54: ...Field Wiring Indoor Units 52 10 Field Wiring...
Страница 57: ...Features Indoor Units 55...
Страница 59: ...Service Space Indoor Units 57 3 Service Space...
Страница 60: ...Wiring Diagrams Indoor Units 58 4 Wiring Diagrams LICH4012021T431E 1 LICH4018021T431E...
Страница 64: ...Field Wiring Indoor Units 62 10 Field Wiring LICH4012021T431E 1 LICH4018021T431E...
Страница 67: ...Dimensions Outdoor Units 65 Model KBtu h Unit mm W D H W1 A B 48 60 952 415 1333 1045 634 404...
Страница 69: ...Wiring Diagrams Outdoor Units 67 3 Wiring Diagrams LIHP012000T431E...
Страница 70: ...Wiring Diagrams Outdoor Units 68 LIHP018000T431E LIHP024000T431E...
Страница 71: ...Wiring Diagrams Outdoor Units 69 LIHP036000T431E...
Страница 72: ...Wiring Diagrams Outdoor Units 70 LIHP036000M431E...
Страница 73: ...Wiring Diagrams Outdoor Units 71 LIHP048000T431E LIHP048000M431E LIHP060000M431E...
Страница 98: ...Refrigerant pipe installation Installation 96...