20
4.2
CHILLER STARTUP
Clean the application water circuit with tap water to be sure that there are no free particles. Otherwise, the
filter element can block up during the startup process.
Turn Off the Main power switch (to avoid any possibility of unexpected startup of the equipment during this
operation). Open the lateral panel, open the tank cover and fill the tank with water of the required quality
(see annex 11.1) and the suitable glycol concentration according to point 4.1 of this manual. Using the
Refrifluid B consumable is strongly recommended to maintain the water quality. Fill the tank directly until the
maximum level of the tank is reached. On UC 50 to UC 100 models, lift the level switch manually to make
sure it resets itself: when it
resets you will hear its contact “click”.
While filling the tank, make sure no water splashes onto any electrical components. Keep the cover of the
electrical box closed during the filling procedure.
Prime the pump to release any air inside:
Remove the priming plug (P, see diagram below).
Keep the priming plug open until only liquid runs out the priming plug.
Replace the priming plug and tighten securely.
Do not start the Ultracool unit until the pump has been properly vented.
Open the water inlet valve completely and close the outlet water valve completely as shown on the following
picture:
Make sure that the external fuses are installed, see point 3.6.
Switch OFF the main power switch during any electrical intervention.
Connect the Remote ON/OFF control in terminals 23 and 24. If you do not use a remote control, connect
the wire-bridge supplied inside the electrical box to link terminals 23 and 24.