44428235
ASSEMBLY INSTRUCTION
Valid from:
17.07.2019
EPIC
®
SOLAR 4 PLUS
Document: L44428235EN
Version: 02
Page 9 of 9
We reserve all rights according to DIN ISO 16016.
Laying the cable
The cables must be laid firmly in the photovoltaic system, securely fastened and the minimum
bending radius shall not be undercut. The cable shall be led out staight at least L=50 mm. The
bending radius Rmin must be at least 10x cable diameter.
U.I. Lapp GmbH
Schulze- Delitzsch- Straße 25
70565 Stuttgart
Tel.: +49 (0) 711 7838-01
Fax.: + 49 (0) 711 7838 2640