5 Installation at Site
30 of 104
mini-Compacta
2317.886/16-EN
– Head H = H
Geodetic
+ H
Losses
Manual drainage
For manual drainage of the installation site observe the following:
▪
Minimum pit dimensions 300 × 300 × 500 mm
▪
Hand diaphragm pump available as accessory
5.6 Electrical connection
DANGER
Electrical connection work by unqualified personnel
Risk of fatal injury due to electric shock!
▷
Always have the electrical connections installed by a trained and qualified
electrician.
▷
Observe regulations IEC 60364 and, for explosion-proof models, EN 60079.
WARNING
Incorrect connection to the mains
Damage to the mains network, short circuit!
▷
Observe the technical specifications of the local energy supply companies.
CAUTION
Wrong supply voltage
Damage to the lifting unit!
▷
The maximum permissible deviation in supply voltage is 10 % of the rated
voltage indicated on the name plate.
Lightning protection
▪
Electrical installations must be protected against overvoltage (compulsory since
14 December 2018) (see DIN VDE 0100-443 (IEC60364-4-44:2007/A1:2015,
modified) and DIN VDE 0100-534 (IEC 60364-5-53:2001/A2:2015, modified).
Whenever modifications are made to existing installations, retrofitting a surge
protective device (SPD) in accordance with VDE is mandatory.
▪
A maximum cable length of 10 metres should not be exceeded between the
surge protective device (usually type 1, internal lightning protection) installed at
the service entrance and the equipment to be protected. For longer cables,
additional surge protective devices (type 2) must be provided in the sub-
distribution board upstream of the equipment to be protected or directly in the
equipment itself.
▪
The associated lightning protection concept must be provided by the operator or
by a suitable provider commissioned by the operator. Surge protective devices
can be offered for the control units on request.
Connecting the LevelControl Basic 1 control unit
ü
The mains voltage at the site has been verified against the data on the name
plate.
1. Connect the control unit to the output of the external master switch housing
with a suitable cable. Guide the mains cable into the master switch housing. Use
suitable cable glands.
2. Establish the connection in accordance with the wiring diagram.