7 Servicing/Maintenance
84 of 116
CHTRa
7.3.4.3 Checking the shaft ends for run-out
Fig. 36:
Checking the shaft ends for run-out
NOTE
Observe the marking between coupling hub and shaft. (
1. Permissible tolerance at the pump shaft ≤ 0.03 mm. If this value is exceeded,
contact KSB.
2. Permissible tolerance of the motor shaft, see the data provided by the
manufacturer.
7.3.5 Removing the pump from the system (if necessary)
7.3.5.1 Dismantling the piping and instruments
1. Have a container on hand for both the fluid handled and the supplies and, if
required, place it underneath the connections of the pipes to be dismantled.
2. Secure inlet and discharge lines.
3. Undo the connections between discharge nozzle and discharge line and
between suction nozzle and suction line.
4. Dismantle the minimum flow valve, if installed.
5. Disconnect the tapping pipe, if applicable.
6. Detach and dismantle any auxiliary lines such as balancing liquid, circulation,
cooling liquid and oil pipes or measuring lines as far as necessary.
7. Dismantle the measuring instruments as far as necessary, and store them
appropriately.
8. If required, dismantle the shaft seal cooler including support.
9. Dispose of the fluid handled and the supplies in compliance with environmental
standards.
10. Close the openings of all dismantled pipes.
Содержание CHTRa
Страница 1: ...Process Pump CHTRa Installation Operating Manual...
Страница 112: ...10 Related Documents 112 of 116 CHTRa 10 5 Order specific documents...
Страница 114: ...Index 114 of 116 CHTRa W Warnings 9 Warranty claims 7 Weight 110...
Страница 115: ......
Страница 116: ...KSB SE Co KGaA Johann Klein Stra e 9 67227 Frankenthal Germany Tel 49 6233 86 0 www ksb com 2700 81 03 EN...