5 Installation at Site
45 of 116
CHTRa
NOTE
A motor protection device is recommended.
5.17.1 Earthing
DANGER
Electrostatic charging
Explosion hazard!
Fire hazard!
Damage to the pump set!
▷
Connect the PE conductor to the earthing terminal provided.
5.17.2 Connecting the motor
NOTE
In compliance with IEC 60034-8, three-phase motors are always wired for clockwise
rotation (looking at the motor shaft stub).
The pump's direction of rotation is indicated by an arrow on the pump.
1. Match the motor's direction of rotation to that of the pump.
2. Observe the manufacturer's product literature supplied with the motor.
5.18 Final installation of the pump set
▪
Check coupling alignment and re-align, if necessary.
Consider height and lateral displacements in accordance with the assembly
sketch.
If the connection of the pipe has altered the pump set’s alignment, the pipe is
not free from stresses or strains.
▪
Record the final measurement results in the coordinate system of the alignment
data sheet/transfer log of the coupling.
5.18.1 Fastening the pump feet
1. Tighten the nuts on the suction side/drive end in accordance with the
specifications on how to fasten the pump feet. Observe the tightening torque.
2. Tighten the nuts on the discharge side/non-drive end so that the discs may still
be moved by means of slight hammer blows.
3. Lock all nuts using an additional nut.
5.18.2 Pinning the pump feet
Fig. 25:
Pinning the pump feet
Содержание CHTRa
Страница 1: ...Process Pump CHTRa Installation Operating Manual...
Страница 112: ...10 Related Documents 112 of 116 CHTRa 10 5 Order specific documents...
Страница 114: ...Index 114 of 116 CHTRa W Warnings 9 Warranty claims 7 Weight 110...
Страница 115: ......
Страница 116: ...KSB SE Co KGaA Johann Klein Stra e 9 67227 Frankenthal Germany Tel 49 6233 86 0 www ksb com 2700 81 03 EN...