10 Operation
10.2 Commissioning
10.2 Commissioning
10.2.1
Cleaning the pipe system
Notice
Soiling in the pipe system impairs the service life of the pump station. If the pipe system is flushed us-
ing the pump station during the initial commissioning, an additional commissioning filter has to be in-
stalled temporarily before the pump station. Alternatively the strainers supplied as standard can be re-
placed during commissioning by fine-meshed commissioning strainers.
Personnel qualification:
o
Fitter
Personal protective equipment:
o
Work clothing
o
Protective gloves
o
Protective helmet
o
Safety boots
ATTENTION
Damage to device through impurity in the pipe system.
► During welding work attach protective covers in front of the connecting flanges.
► Ensure when welding that welding beads and abrasive dust cannot get into the pipe system and
the pump station.
► Ensure that a commissioning filter is installed when the pipe system is flushed and cleaned using
the pump.
ATTENTION
Damage to equipment through additional pressure loss in the commissioning filter/commis-
sioning strainer.
► Calculate the flow resistance and determine the remaining pump intake.
► Monitor the suction-side pressure.
► Check the commissioning filter/commissioning strainer regularly.
Requirement:
ü
If required, commissioning filter/commissioning strainer installed (mesh width 0.02 mm)
1.
Clean the complete pipe system before commissioning in order to protect the pump station.
2.
Flush the pipe system at least 50 – 100 hours.
10.2.2
Filling and venting the pump station
Possibilities
There are two possible ways to fill the pump station:
o
Via the suction connection or pressure connection
o
Via the strainers
Filling and venting the pump station via the suction connection or pressure connection
Personnel qualification:
o
Fitter
Personal protective equipment:
o
Work clothing
o
Protective gloves
o
Protective helmet
o
Safety boots
o
Face protection
Aids:
o
Collection tank
30
OID 02en-GB Edition 2019-11
Operating instructions