14 Installation Note N5245-90012
Installation Procedure for the Upgrade
-
“Step 23. Install the A10 26.5 GHz Source 2 Assembly and Cables.”
“Step 24. Install the A17 13.5 GHz (Source 2) Synthesizer Board and Cables.”
“Step 25. Install the Test Set Cables.”
“Step 26. Secure the Front Panel Bulkhead Connectors.”
“Step 27. Reinstall the A23 Test Set Motherboard.”
“Step 28. Disassemble the 2-Port Front Panel and Assemble the 4-Port Front
Panel.”
“Step 29. Reinstall Front Panel Assembly.”
“Step 30. Install the Overlays.”
“Step 31. In stall the Front Panel Jumper Cables.”
“Step 32. Position the Cables and Wires to Prevent Pinching.”
“Step 33. Reinstall the Inner Cover.”
“Step 34. Reinstall the Outer Cover.”
“Step 35. Remove Option 219 License.”
“Step 36. Enable Options P04 (400) and 419.”
“Step 37. Perform Post-Upgrade Adjustments and Calibration.”
“Step 38. Prepare the PNA for the User.”
Step 1.Obtain a Keyword and Verify the Information
Follow the instructions on the Option Entitlement Certificate supplied to obtain
a license key for installation of this upgrade. Refer to
Verify that the model number, serial number, and option number information
on the license key match those of the instrument on which this upgrade will be
installed.
If the model number, serial number, or option number do not match those on
your license key, you will not be able to install the option. If this is the case,
contact Keysight for assistance before beginning the installation of this
upgrade. Refer to
“Contacting Keysight” on page 4
Once the license key has been received and the information verified, you can
proceed with the installation at step 2.
Step 2. Remove the Outer Cover
For instructions, click the Chapter 7 bookmark “Removing the Covers” in the
PDF Service Guide
1
.
1. See