Switch actuator, 2-gang / blinds actuator, 1-gang

4.2 Commissioning

Commissioning the device

NOTICE!

Incorrect load control due to undefined relay state at delivery.

Risk of destruction of connected drive motors.

During commissioning, before switching on the load, ensure that all relay contacts
are open by applying the KNX bus voltage. Observe commissioning sequence!

Switch on the KNX bus voltage.

Wait about 10 s.

Connect the load circuit.

Delivery state: The output is set as a blind output. Operation of the blind output possible
via input 1 (UP) and input 2 (DOWN). Input 3 has no function.

Function of Inputs in the as-delivered state

Input

Push-button (NO contact)

Function

1

Press briefly (< 0.4 s)

Stop

1

Press briefly (< 0.9 s)

Adjusting the slats UP

1

Press for a long time (> 0.9
s)

Raise

2

Press briefly (< 0.4 s)

Stop

2

Press briefly (< 0.9 s)

Adjusting the slats DOWN

2

Press for a long time (> 0.9
s)

Lower

3

---

---

Load physical address and application program

For switched loads, configure the outputs as a switching output.

For Venetian blind operation, configure the outputs as a Venetian blind output.

In Venetian blind operation: measure blind/shutter and slat travel times and enter them in
the parameter setting.

Press the programming button.
The programming LED lights up.

Load physical address and application program using the ETS.

Safe-state mode

The safe state mode stops the execution of the loaded application program.

Only the system software of the device is still functional. ETS diagnosis functions and pro-
gramming of the device are possible.

Activating the safe-state mode

Switch off the bus voltage or disconnect the device from the KNX.

Wait about 10 s.

Press and hold down the programming button.

Switch on the bus voltage or connect the device to KNX. Release the programming button
only after the programming LED starts flashing slowly.
The safe-state mode is activated.

6 / 9

82404203

26.01.2021

J0082404203

Содержание KNX 230021 SU

Страница 1: ... voltage cores Danger of electric shock on the KNX installation Do not connect any external voltage to the in puts The device might be damaged and the SELV potential on the KNX bus line will no longer be available For parallel connection of several motors to an output it is essential to observe the correspond ing instructions of the manufacturers and to use a cut off relay if necessary The motors ...

Страница 2: ...in building automation and can be configured in the ETS project Detailed specialist know ledge is required A device certificate which is attached to the device is required for safe com missioning During mounting the certificate must be removed from the device and stored se curely Planning installation and commissioning of the device are carried out with the aid of the ETS version 5 7 3 and above I...

Страница 3: ...d slat position Forced position through higher level controller Safety function 3 independent wind alarms rain alarm frost alarm Sun protection function with heating cooling operation Disabling function lock out protection Scene function Characteristics extension inputs Switching operating function Dimming operating function incl colour temperature dimming Shutter Venetian blinds operating functio...

Страница 4: ... separate appliance boxes Connecting and fitting the device In secure operation preconditions Secure commissioning is activated in the ETS Device certificate entered scanned or added to the ETS project A high resolution camera should be used to scan the QR code Document all passwords and keep them safe Mounting in suitable appliance box recommendation electronic device box with partition Ob serve ...

Страница 5: ...rrect polarity Connect load as shown in the connection example Figure 5 If required connect potential free contacts or dew leakage sensors to inputs 1 3 or NTC temperature sensors to input 3 Figure 2 Install the device in the appliance box In secure operation The device certificate must be removed from the device and stored securely The COM reference potential must not be connected together with C...

Страница 6: ...WN 2 Press for a long time 0 9 s Lower 3 Load physical address and application program For switched loads configure the outputs as a switching output For Venetian blind operation configure the outputs as a Venetian blind output In Venetian blind operation measure blind shutter and slat travel times and enter them in the parameter setting Press the programming button The programming LED lights up L...

Страница 7: ... restarts and is ready for operation again after ap prox 5 s Restoring the device to factory settings Devices can be reset to factory settings with the Jung ETS Service App This function uses the firmware contained in the device that was active at the time of delivery delivery state Restor ing the factory settings causes the devices to lose their physical address and configuration 5 Technical data...

Страница 8: ...ing current per unit referred to Σ 16 A per 5 C in excess of 35 C 10 when installed in wooden or dry construction walls 15 when installed in multiple combinations 20 Clampable conductor cross section single stranded 0 5 4 mm Finely stranded without conductor sleeve 0 5 4 mm Finely stranded with conductor sleeve 0 5 2 5 mm Connection torque screw terminals Max 0 8 Nm inputs Control cable pretermina...

Страница 9: ...tor 2 gang blinds actuator 1 gang ALBRECHT JUNG GMBH CO KG Volmestraße 1 58579 Schalksmühle GERMANY Telefon 49 2355 806 0 Telefax 49 2355 806 204 kundencenter jung de www jung de 9 9 82404203 26 01 2021 J0082404203 ...

Отзывы: