6 Installation
6
Installation
6.1
Prepare installation
Requirements:
•
Check the environmental influences to which the device will be exposed.
•
Switch off the plant's voltage and secure it so that it cannot switch on again.
•
Stop medium circulation in the plant.
•
Drain and flush the pipe.
•
Wear suitable protective equipment.
•
Correctly prepare the pipe for installation.
•
Use only suitable tools when working on the device and plant.
Inlet and outlet sections
Installation position
To calm the flow in the pipeline,
the specified inlet and outlet sec-
tions are required at the very
least.
For increased accuracy, the inlet
and outlet sections can be made
longer.
DN = Nominal pipe width
= Flow direction
1× 90° manifold or T-piece
2× 90° manifolds
Pipe extension
Pipe reduction
3× DN
5× DN
3× DN
5× DN
3× DN
5× DN
3× DN
5× DN
Mount the device in either the hor-
izontal or vertical pipe.
Requirements:
•
The pipe around the transduc-
ers must be filled.
•
The flow direction (
) must
run upward when mounting
vertically.
•
Avoid the formation of air bub-
bles in the pipe and right at
the device.
Correct
Incorrect