Installation
3.4
Commissioning
Prior to initial commissioning (or to com-
missioning after maintenance work) fill the
installed device with water and vent:
1.
Open the upstream shut-off valve to
fill the device with water. The device is
now under mains pressure.
2.
Fully open a water tap downstream of
the device. After a flushing water quan-
tity of about 5 litres, the device is bled.
3.
Plug the power supply unit in.
The control system checks the position
of the shut-off valve. If the shut-off valve
is open, the display shows:
Initial position
leakage protect
The device is ready for operation.
4
Operation
4.1
Status display
During normal operation the status dis-
play is displayed:
Leakage protect
opened
Letter “L“ at the end of the 2nd line:
•
“L”: The device is in learning mode (see
chapter 4.4.3).
4.2
Possible settings
The following settings can be made via
the key
Menu
(Selection
Setting
):
Submenu
item
Setting
Language
German, English, French,
Dutch, Italian
Submenu
item
Setting
Leakage pro-
tection (see
Limit values
Vacation mode
Sleepmode time
Auto. testing (micro leak-
age testing)
Date
Day / month / year
Time
Hours / minutes
Backlight
10 % to 100 %, in 10%
steps
Contrast
10 % to 100 %, in 10%
steps
Tone
Off / on / interval 6 h
Message
relay
Set fault indication relay as
normally closed contact /
normally open contact
Factory set-
ting
Recreate factory setting;
see chapter 4.2.1)
Procedure:
1.
Press
Menu
key.
2.
Navigate to
Setting
using the arrow
keys and confirm with the
OK
key.
3.
Navigate to the desired setting
(e.g.
date) and confirm with the
OK
key.
4.
Using the arrow keys navigate to the
desired setting (e.g. set date) and con-
firm with the
OK
key.
1703593 • 2022/10
JUDO JPCS