• The critical load change condition to prevent an overcooling trip of the chiller is 5% / minimum
maximum.
Set the steam feed pressure at the inlet of the steam control valve to the specified level. If the
pressure is lower than the specification, the result is insufficient performance. Limit the steam
pressure fluctuation in the range of the specification value +7/-14 psig. If the pressure fluctuation
is too big, control becomes unstable. The valve seeks the correct chilled water temperature at the
outlet. As a result, the performance suffers and the operation can stop.
Install a 60 ~ 70 mesh strainer in front of the shut-off valve.
Use the regulator valve on the facility side to adjust the pressure at the steam drain outlet to match
the specification.
If air or steam flows back while the chiller is stopped, install a check valve in the middle of the drain
return piping.
If two or more chillers are installed and their drain return pipes are joined to return the drain to the
hot well tank, install the check valve before the junction of the pipes.
To prevent an inflow of drain liquid to the generator, install a drain trap at the lowest point of the
control valve inlet side.
If there is too much mist in the steam, install a mist separator.
A drain trap does not need to be installed in the steam drain line between the chiller and the hot
well tank. The condensed water draining from the chiller is sub-cooled enough that a drain trap is
unnecessary.
Isolate the main steam supply valve when you service the chiller or there is an extended shut down.
Chilled water outlet temperature controller
The chilled water outlet temperature controller is located on the sequencer and controls the chilled
water outlet temperature.
Liquid level gauges
Liquid level gauges are used to check the condition of the chiller components.
Table 22: Liquid level gauges
Liquid level gauge name
Symbol
Function
Refrigerant overflow monitoring level gauge
G101
Checks refrigerant overflow level
Refrigerant tank level gauge
G102
Checks lower limit of refrigerant tank level
Absorber level gauge
G103
Checks lower limit of absorber
Generator level gauge
G104
Checks condition of solution in generator
Starting the chiller
Before starting the chiller, inspect the following items:
• Check that the refrigerant blow valve (V8) is closed.
• Check the degree of the vacuum in the machine. Use the pressure gauge of the generator.
• Check that the steam supply valve is open.
• Open the steam shut off valve.
• Keep the steam inlet pressure at the specification.
• Check that the Refrigerant Pump
Auto
button is pressed.
99
YHAU-C Single Effect Steam-Fired Absorption Chiller
Содержание York YHAU-C
Страница 2: ......
Страница 26: ...Figure 6 Fitting tir rollers to the machine YHAU C Single Effect Steam Fired Absorption Chiller 24...
Страница 33: ...Figure 11 Location of rupture disk 31 YHAU C Single Effect Steam Fired Absorption Chiller...
Страница 85: ...Figure 37 PLC and touch screen communication wiring 83 YHAU C Single Effect Steam Fired Absorption Chiller...
Страница 103: ...Figure 49 Cooling start diagram 101 YHAU C Single Effect Steam Fired Absorption Chiller...
Страница 104: ...Figure 50 Cooling stop diagram YHAU C Single Effect Steam Fired Absorption Chiller 102...
Страница 166: ...Figure 73 Steam and drain system YHAU C Single Effect Steam Fired Absorption Chiller 164...
Страница 167: ...Figure 74 Duhring diagram PTX chart F 165 YHAU C Single Effect Steam Fired Absorption Chiller...
Страница 168: ...Figure 75 Duhring diagram PTX chart C YHAU C Single Effect Steam Fired Absorption Chiller 166...
Страница 169: ...Figure 76 Specific gravity concentration F 167 YHAU C Single Effect Steam Fired Absorption Chiller...
Страница 170: ...Figure 77 Specific gravity concentration C YHAU C Single Effect Steam Fired Absorption Chiller 168...
Страница 178: ...Figure 79 Troubleshooting sequence flow chart YHAU C Single Effect Steam Fired Absorption Chiller 176...