Section 2 - Pre-Operation and Inspection
2-1
31200749
SECTION 2 - PRE-OPERATION AND INSPECTION
2.1
PRE-OPERATION CHECK AND INSPECTION
Note:
Complete all required maintenance before operating unit.
The pre-operation check and inspection, performed at beginning of each work shift
or at each change of operator, should include the following:
1.
Cleanliness
- Check all surfaces for leakage (oil, fuel or battery fluid) or foreign
objects. Report any leakage to the proper maintenance personnel.
2.
Structure
- Inspect the machine structure for dents, damage, weld or parent
metal cracks or other discrepancies.
3.
Safety Decals
- Ensure all safety decals are legible and in place. Clean or
replace as required. See page 2-3 for details.
4.
Operation and Safety Manuals
- Operation & Safety Manual and AEM Safety
Manual (ANSI only) are located in cab manual holder.
5.
Walk-Around Inspection
- See page 2-10 for details.
6.
Fluid Levels
- Check fluids, including fuel, hydraulic oil, engine oil, transmission
fluid and coolant. When adding fluids, refer to Section 7 - Lubrication and
Maintenance and Section 9 - Specifications to determine proper type and
intervals. Before removing filler caps or fill plugs, wipe all dirt and grease away
from the ports. If dirt enters these ports, it can severely reduce component life.
7.
Attachments/Accessories
- Ensure correct capacity charts are installed on the
telehandler. If provided, reference the Operation & Safety Manual of each
attachment or accessory installed for specific inspection, operation and
maintenance instructions.
WARNING
FALL HAZARD.
Use extreme caution when checking items beyond your normal
reach. Use an approved ladder.
O
A
H
1000
PARENT METAL CRACK
WELD CRACK
Содержание Skytrak 10042
Страница 3: ...Revision Log a 31200749 Revision Log REVISION LOG March 30 2012 A Original Issue of Manual ...
Страница 24: ...Section 1 General Safety Practices 1 14 31200749 This Page Intentionally Left Blank ...
Страница 33: ...Section 2 Pre Operation and Inspection 2 9 31200749 This Page Intentionally Left Blank ...
Страница 70: ...Section 4 Operation 4 12 31200749 This Page Intentionally Left Blank ...
Страница 75: ...Section 5 Attachments 5 5 31200749 This Page Intentionally Left Blank ...
Страница 79: ...Section 5 Attachments 5 9 31200749 This Page Intentionally Left Blank ...
Страница 106: ...Section 5 Attachments 5 36 31200749 This Page Intentionally Left Blank ...
Страница 116: ...Section 7 Lubrication and Maintenance 7 8 31200749 10054 OH4242 50 EVERY ...
Страница 117: ...Section 7 Lubrication and Maintenance 7 9 31200749 250 Hour Lubrication Schedule 6036 6042 OA1820 EVERY 250 6042 ONLY ...
Страница 118: ...Section 7 Lubrication and Maintenance 7 10 31200749 8042 10042 10054 OH4172 EVERY 250 ...
Страница 119: ...Section 7 Lubrication and Maintenance 7 11 31200749 1000 Hour Lubrication Schedule OH4181 1000 EVERY ...
Страница 148: ...Index 4 31200749 ...
Страница 150: ...Inspection Maintenance and Repair Log Date Comments ...
Страница 152: ......