Installation Instructions 

JATCO Environmental Protection Tank 

J-5000

 SM-P

*INSTRUMENTATION GAS IS MANDATORY FOR SUPPLY GAS*

The JATCO Environmental Tank must be installed at a level which will allow the waste liquids to be 
disposed of to gravity flow into the tank. 

IMPORTANT: The top of the tank must be below the level of waste liquids to be received.

 

Inlet and the outlet check valves are both teed from the same port near the bottom of the tank (end opposite 
the sight glass). When facing this end, the inlet check valve  is on the left 

(A)

  and the outlet check valve 

is on the right 

(B)

The discharge should be piped directly to the storage tank that is to receive the waste liquid. The discharge 
may be teed into an existing flow line, provided that a high-pressure check valve (1000 psi) is installed to 
prevent high pressure from returning to the discharge check valve on the JATCO tank. 

The tank supply gas must have adequate 

volume

 and pressure. For best operation use 1” pipe for the tank 

supply gas plumed as close to the tank as possible. Then reduce down to the tubing connection 

(C) 

on the 

JATCO tank.  

Supply gas pressure 

minimum 

(

4

0 psi) is connected to the bottom inlet of the 

level control

 

valve 

(C)

 

this gas pressure must not exceed (

75 

psi) for normal operation. No pressure regulator is provided

.

G

auge cock knobs are removed for shipping. 

Depressing the manual dump plunger allows the operator to check function of the float and 

level control

 

valve

. When the plunger is depressed, the tank will cycle

 

once and return to the automatic operation. 

The plunger button should be returned to the extended position. 

3-

way pilot valve 

(G)

 is vented thru ¼” NPT port 

(H)

.

Liquid levels in the JATCO tank may be observed in the sight glass furnished as standard 
equipment. 

244 N.W. 111