Float Arm Assembly
TOOLS REQUIRED:
(2) 19mm wrench
19mm socket wrench (optional)
STEP 1:
Reference the previous page to
select which float arm connection hole is
required for your machine.
IMPORTANT:
Be sure to use the proper hole
to avoid a prolonged installation.
STEP 2:
Locate the 3 float arm assemblies.
Have the M12 x 90mm long bolts and M12
nylok nuts easily accessible near the core unit
assembly.
STEP 3:
Take the float arm and slip the
narrow end with Float Arm Stems around the
core unit leg. Align the holes through the
Float Arm Stems with the correct float arm
connection hole determined from Step 1.
STEP 4:
Once aligned slide the M12 X 90mm
bolt through all holes. Tighten a M12 nylok nut
onto the bolt until there is little play or space
between the bolted components. Use a two
19mm wrenches to tighten nut.
STEP 5:
Repeat steps 2 and 3 for the other 2
float arms.
©2022 IXOM Watercare Inc. | www.ixomwatercare.com | 866 - 437 - 8076 | [email protected]