9.4. Consumption grid connection process
To connect the consumption grid:
L
Line
N
Neutral
Ground
1. Loosen the packing gland marked
LOADS
(see section
“2.7. Description of cable inlets”
), remove the cap
and pass the consumption grid cable through it.
2. Use two of the ferrite cores supplied with the unit and make two turns with the
L
and
N
wiring from the
storage system.
3. Connect the
push-in
type terminals marked as
J56
LOADS
, respecting the polarities. The operation of
this type of terminal is described in
“7. Connection/disconnection of wiring in push-in type terminals”
.
4. Correctly tighten the cable gland to prevent losses to the protection class, verifying that the wiring is not
taut.
30
Connecting the consumption grid
Ingeteam
Содержание INGECON SUN STORAGE 1Play
Страница 1: ...INGECON SUN STORAGE 1Play Installation and Operation Manual ...
Страница 70: ...Notes ...
Страница 72: ...ABH2015IQE01_ 12 2021 Ingeteam Power Technology S A www ingeteam com ...